Legislation Details

File #: 24-2279    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/22/2024 In control: Department of Public Works
On agenda: 8/14/2024 Final action:
Title: Authorize an increase in the contract (1) for additional funding to the 2024 Annual Street Maintenance Improvement Contract to complete the projects proposed in the 2024 Annual Street Maintenance Improvement Contract, in an amount not to exceed $21,290,118.00, increasing the contract from $85,160,474.50 to $106,450,592.50; and (2) extend the term of the contact to an additional 180 calendar days to complete the projects proposed in the contract - Not to exceed $21,290,118.00, from $85,160,474.50 to $106,450,592.50 - Financing: General Fund (subject to annual appropriation)
Indexes: 100
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: August 14, 2024
COUNCIL DISTRICT(S): All
DEPARTMENT: Department of Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the contract (1) for additional funding to the 2024 Annual Street Maintenance Improvement Contract to complete the projects proposed in the 2024 Annual Street Maintenance Improvement Contract, in an amount not to exceed $21,290,118.00, increasing the contract from $85,160,474.50 to $106,450,592.50; and (2) extend the term of the contact to an additional 180 calendar days to complete the projects proposed in the contract - Not to exceed $21,290,118.00, from $85,160,474.50 to $106,450,592.50 - Financing: General Fund (subject to annual appropriation)

Body
BACKGROUND

On January 24, 2024, the City Council authorized a construction contract with Texas Materials Group, dba TexasBit, a CRH company, for the 2024 Annual Street Maintenance Improvement Contract, in an amount not to exceed $85,160,474.50, by Resolution No. 24-0171.

It was determined that additional funding to the 2024 Annual Street Maintenance Improvement Contract was needed to complete the projects proposed in the 2024 Annual Street Maintenance Improvement Contract and that we needed to extend the term of the contract to an additional 180 calendar days to complete the projects proposed in the contract.

ESTIMATED SCHEDULE OF PROJECT

Began Construction January 2024
Complete Construction August 2025

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On January 24, 2024, the City Council authorized a construction contract with Texas Materials Group, dba TexasBit, a CRH company, for the 2024 Annual Street Maintenance Improvement Contract by Resolution No. 24-0171.

FISCAL INFORMATION

Fund
FY 2024
FY 2025
Future Years
General Fund
$0.00
$21,290,118.00
$0.00

Construction Contract $ 85,160,474.50
Change Order No. 1 (this ...

Click here for full text