File #: 26-251A    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 1/7/2026 In control: Dallas Water Utilities Department
On agenda: 2/25/2026 Final action:
Title: Authorize a construction services contract for the Hillcrest Road Pump Station House Project - Big Sky Construction Company, Inc., lowest responsible bidder of four - Not to exceed $1,779,000.00 - Financing: TxDOT RTR Hillcrest Pump House Fund *In alignment with Capital Improvement Program.
Indexes: 12
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     February 25, 2026

COUNCIL DISTRICT(S):                     12

DEPARTMENT:                     Dallas Water Utilities Department

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the Hillcrest Road Pump Station House Project - Big Sky Construction Company, Inc., lowest responsible bidder of four - Not to exceed $1,779,000.00 - Financing: TxDOT RTR Hillcrest Pump House Fund

 

*In alignment with Capital Improvement Program.

 

Body

BACKGROUND

 

Dallas Water Utilities Department’s (DWU) Stormwater Operations is responsible for the maintenance and operation of the City’s drainage system. To accommodate the Dallas Area Rapid Transit (DART) Silver Line, Hillcrest Road was lowered and the Hillcrest Pump Station was constructed to provide flood mitigation and enhance public safety associated with these public improvements. The pump station is located at the prominent and highly visible intersection of McCallum Boulevard and Hillcrest Road. The proposed project includes an enclosure that will support Stormwater Operations by protecting critical drainage infrastructure and mitigating environmental impacts, including visual and noise effects, associated with the City’s stormwater pump station. Jacobs Engineering Group, the project’s retained consultant engineer, designed a house-like enclosure to surround the existing pump station equipment and reflect the architectural character of the adjacent residential area.

 

This action will authorize a construction services contract with Big Sky Construction Company, Inc. for the construction of the Hillcrest Road Pump Station House Project enclosure. The site is located at 17404 Hillcrest Road at the corner of Hillcrest Road and McCallum Boulevard across from the Northeast Dallas Police Substation.  The construction is to be funded by the North Central Texas Council of Governments (NCTCOG) with a total available construction budget of $1.8M.

 

Big Sky Construction Company, Inc. has had no contractual activities with the City of Dallas for the past three years.

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          April 2026

Complete Construction                     April 2027

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On April 9, 2025, the City Council authorized the acceptance of Regional Toll Revenue funds from the State of Texas, acting by and through the Texas Department of Transportation (TxDOT), within the North Central Texas Council of Governments (NCTCOG) Metropolitan Planning Area.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

TxDOT RTR Hillcrest Pump House Fund

$1,779,000.00

$0.00

$0.00

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Big Sky Construction Company, Inc.

Local

4.76%

 

PROCUREMENT INFORMATION

 

The following four bids with quotes were received on November 21, 2025:

 

*Denotes successful bidder

 

Bidders                                                                                                                                Bid Amount

 

*Big Sky Construction Company, Inc                                           $1,779,000.00

 507 Exposition Avenue

 Dallas, Texas 75226

Talley Riggins Construction Group                     $1,879,000.00

Real Construction Group                     $2,180,359.38

CLW Water Group                                                                                                         $4,250,000.00

 

OWNER/EXECUTIVE

 

Big Sky Construction Company, Inc.

 

Bob Long, President

 

MAP

 

Attached