File #: 25-1290A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 4/9/2025 In control: Department of Aviation
On agenda: 5/28/2025 Final action:
Title: Authorize (1) a construction services contract for the demolition, removal, reconstruction, realignment, and rehabilitation of Taxiway Charlie, and for connection taxiways services for the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field; (2) an increase in appropriations in an amount not to exceed $15,151,277.00 in the Aviation AIP Grant Fund; (2) an increase in appropriations in an amount not to exceed $2,317,870.86 in the Aviation Construction Fund; and (3) an increase in appropriations in an amount not to exceed $18,218,232.00 2,873,311.00 in the Aviation Passenger Facility Charge - Near Term Projects Fund - Flatiron Dragados Constructors, Inc., lowest responsible bidder of three - Not to exceed of $20,536,102.86 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund ($18,218,232.00 3,066,955.00) and Aviation Construction Fund ($2,317,870.86) and Aviation AIP Grant Fund ($15,151,277.00) (see fiscal information)
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     May 28, 2025

COUNCIL DISTRICT(S):                     6

DEPARTMENT:                     Department of Aviation

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize (1) a construction services contract for the demolition, removal, reconstruction, realignment, and rehabilitation of Taxiway Charlie, and for connection taxiways services for the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field; (2) an increase in appropriations in an amount not to exceed $15,151,277.00 in the Aviation AIP Grant Fund; (2) an increase in appropriations in an amount not to exceed $2,317,870.86 in the Aviation Construction Fund; and (3) an increase in appropriations in an  amount not to exceed $18,218,232.00 2,873,311.00 in the Aviation Passenger Facility Charge - Near Term Projects Fund - Flatiron Dragados Constructors, Inc., lowest responsible bidder of three - Not to exceed of $20,536,102.86 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund ($18,218,232.00 3,066,955.00) and Aviation Construction Fund ($2,317,870.86) and Aviation AIP Grant Fund ($15,151,277.00) (see fiscal information)

 

Body

BACKGROUND

 

The need for the rehabilitation of Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field was identified in the 2009 Applied Research Associates, Inc. Pavement Evaluation Report due to the upcoming end of the concrete pavement’s useful life

 

The purpose of the Taxiway Charlie Phase 2 Reconstruction Project at Dallas Love Field is to improve airfield operational resiliency, advance Federal Aviation Administration safety standards, and enhance Dallas Love Field sustainability efforts. Additionally, improvements to airfield lighting and stormwater drainage will also be addressed to enhance airfield operations and reduce negative environmental impacts.

 

The construction of Taxiway Charlie Phase 2 Reconstruction Project encompasses Taxiway C, from east of Taxiway K to the threshold connector to Runway 13R, including the connector to Taxiway L at the western end of Taxiway C (subphase 2A & 2C).

 

 

The following chart illustrates Flatiron Dragados Constructors, Inc., contractual activities with the City of Dallas for the past three years:

 

AVI                     DWU                     PKR                     TPW

 

Projects Completed                     0                     0                     0                     0

Active Project                     0                     0                     0                     0

Change Orders                     0                     0                     0                                          0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                                          0

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                     November 2019

Completed Design                     January 2025

Begin Construction                     June 2025

Complete Construction                     March 2026                     

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On October 23, 2019, the City Council authorized an engineering services contract with HNTB Corporation to provide design and construction administration services for the rehabilitation of Taxiway Charlie at Dallas Love Field by Resolution No. 19-1638.

 

On  April 9, 2025, the City Council authorized the accept of a grant upon receipt from the U.S. Department of Transportation, Federal Aviation Administration (FAA) Airport Improvement Program (AIP) for the federal share of the eligible capital improvement project for the Bipartisan Infrastructure Law at Dallas Love Field (Grant No. TBD, Assistance Listing No. 20.106) in the amount of $10,000,000.00 for the construction of Taxiway Charlie Phase 2 Reconstruction Project where the performance period shall be for four years from the date of acceptance by Resolution No. 25-0562.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Aviation Passenger Facility Charge - Near Term Projects Fund

$18,218,232.00 3,066,955.00

$0.00

$0.00

Aviation Construction Fund

$ 2,317,870.86

$0.00

$0.00

*Aviation AIP Grant Fund

$15,151,277.00

$0.00

$0.00

Total

$20,536,102.86

$0.00

$0.00

 

*This is a passthrough fund not a grant fund.  Funds will be disbursed from the Aviation AIP Grant fund then later reimbursed by a grant fund.

 

 

 

 

DBE INFORMATION

 

In accordance with US CFR 49, Part 26 for Disadvantaged Business Enterprise (DBE) participation on projects wholly or partly funded through federal grant dollars, the DBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

DBE Goal

$20,536,102.86

Construction

8.30%

DBE Subcontracting %

DBE Overall %

DBE Overall Participation $

8.34%

8.34%

$1,712,753.60

This contract exceeds the DBE subcontracting goal.

Flatiron Dragados Constructors, Inc. - Local; Workforce 12.37% Local

 

BID INFORMATION

 

The following three bids were received and opened on March 28, 2025:

 

*Denotes successful bidder

 

Bidders                     Amount

 

*Flatiron Dragados Constructors, Inc.                     $20,536,102.86

 1320 Greenway Drive

 Suite 815

 Irving, TX 75038

GDS, LLC d.b.a. Ambrozi Contracting                     $23,864,324.00

Urban Infraconstruction                     $24,945,000.00

 

OWNER/EXECUTIVE

 

Flatiron Dragados Constructors, Inc.

 

Kurt Knebel, Vice President and District Manager

 

MAP

 

Attached