File #: 20-12    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/12/2019 In control: Department of Transportation
On agenda: 1/22/2020 Final action: 1/22/2020
Title: Authorize a decrease in the construction services contract with Roadway Solutions, Inc. for traffic signal construction of Warranted Traffic Signal Installation Group 6, to remove the construction of the traffic signal located at Interstate Highway 20 Eastbound/Westbound at Mountain Creek Parkway from the contract - Not to exceed ($316,275.00), from $1,337,393.00 to $1,021,118.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
Indexes: 3
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     January 22, 2020

COUNCIL DISTRICT(S):                     3

DEPARTMENT:                     Department of Transportation

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize a decrease in the construction services contract with Roadway Solutions, Inc. for traffic signal construction of Warranted Traffic Signal Installation Group 6, to remove the construction of the traffic signal located at Interstate Highway 20 Eastbound/Westbound at Mountain Creek Parkway from the contract - Not to exceed ($316,275.00), from $1,337,393.00 to $1,021,118.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

 

body

BACKGROUND

 

On August 14, 2019, City Council authorized a construction contract with Roadway Solutions, Inc. for traffic signal construction of Warranted Traffic Signal Installation Group 6 at the following four locations: Singleton Boulevard at Kingbridge Street; Interstate Highway 20 Eastbound/Westbound at St. Augustine Drive; Interstate Highway 20 Eastbound/Westbound at Mountain Creek Parkway; and Lemmon Avenue at Travis Street, in an amount not to exceed $1,337,393.00, by Resolution No. 19-1106.

 

This action will authorize Change Order No. 1 to the construction services contract with Roadway Solutions, Inc. to decrease the funds and remove the Interstate Highway 20 Eastbound/Westbound at Mountain Creek Parkway traffic signal construction from the contract.

 

The intersection is located on the Interstate Highway system. The Texas Department of Transportation System notified the City of their intent to allocate state funds for the installation of the traffic signal located at Interstate Highway 20 and Mountain Creek Parkway. The notification was received after Group 6 was bid. The City reached an agreement with Roadway Solutions, Inc. to remove this traffic signal from the executed Contract No. TRN-2019-00010696.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     January 2020

Complete Construction                     December 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 14, 2019, City Council authorized a construction contract with Roadway Solutions, Inc. for traffic signal construction of Warranted Traffic Signal Installation Group 6 at the following four locations: Singleton Boulevard at Kingbridge Street; Interstate Highway 20 Eastbound/Westbound at St. Augustine Drive; Interstate Highway 20 Eastbound/Westbound at Mountain Creek Parkway; and Lemmon Avenue at Travis Street by Resolution No. 19-1106.

 

FISCAL INFORMATION

 

Fund

FY 2020

FY 2021

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

($316,275.00)

$0.00

$0.00

Total

($316,275.00)

$0.00

$0.00

 

Construction contract                      $1,337,393.00

Change Order No. 1 (this action)                     ($   316,275.00)

 

                     Total                     $1,021,118.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$1,021,118.00

Construction

25.00%

100.00%

$1,021,118.00

This contract exceeds the M/WBE goal.

 

OWNER

 

Roadway Solutions, Inc.

 

Morteza Gamini, Vice President

 

MAP

 

Attached