Legislation Details

File #: 26-2964A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 9/3/2026 In control: Department of Transportation and Public Works
On agenda: 10/28/2026 Final action:
Title: Authorize Amendment No. 1 to the Advance Funding Agreement (Agreement No. CSJ 0918-47-368, Assistance Listing No. 20.205) between the City of Dallas and the Texas Department of Transportation for design and construction for the reconstruction and widening of sidewalks with the installation of pedestrian street lights, and the reconstruction/upgrade of the crosswalks and associated traffic signal infrastructure on Camp Wisdom Road from U.S. Highway 67 to Westmoreland Road in the City of Dallas to delete Attachment B, Project Budget in its entirety and replace with Attachment B-1, Project Budget which revises the indirect state cost calculation formula and the addition of Category 7, Surface Transportation Block Grant funds while reducing Category 5, Congestion Mitigation and Air Quality funds - Financing: This action has no cost consideration to the City (see Fiscal Information) *In alignment with Vision Zero Plan.
Indexes: 3, 8
Attachments: 1. Map, 2. Resolution, 3. Attachment B-1
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     October 28, 2026

COUNCIL DISTRICT(S):                     3, 8

DEPARTMENT:                     Department of Transportation and Public Works

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize Amendment No. 1 to the Advance Funding Agreement (Agreement No. CSJ 0918-47-368, Assistance Listing No. 20.205) between the City of Dallas and the Texas Department of Transportation for design and construction for the reconstruction and widening of sidewalks with the installation of pedestrian street lights, and the reconstruction/upgrade of the crosswalks and associated traffic signal infrastructure on Camp Wisdom Road from U.S. Highway 67 to Westmoreland Road in the City of Dallas to delete Attachment B, Project Budget in its entirety and replace with Attachment B-1, Project Budget which revises the indirect state cost calculation formula and the addition of Category 7, Surface Transportation Block Grant funds while reducing Category 5, Congestion Mitigation and Air Quality funds - Financing: This action has no cost consideration to the City (see Fiscal Information)

 

*In alignment with Vision Zero Plan.

 

Body

BACKGROUND

 

On March 8, 2023, the City Council authorized the acceptance of a grant from the United States Department of Transportation Federal Highway Administration through the Texas Department of Transportation (TxDOT) for the Congestion Mitigation and Air Quality Improvement Program (Agreement No. CSJ 0918-47-368, CFDA No. 20.205) as Federal share in the total project cost of $7,854,750.00 which includes $6,000,000.00 as Federal participation, $354,750.00 as State participation for indirect state cost, and $1,500,000.00 ($1,470,000.00 for design and construction and $30,000.00 for direct state cost paid to TxDOT prior to construction) as local participation for costs related to the reconstruction and widening of sidewalks with the installation of pedestrian streetlights and the reconstruction/upgrade of the crosswalks and associated traffic signal infrastructure on West Camp Wisdom Road from U.S. 67 to South Westmoreland Road in Dallas County by Resolution No. 23-0369.

 

 

 

 

On January 8, 2025, the City Council authorized a professional engineering services contract with Gresham Smith, most highly qualified proposer of four, to develop preliminary engineering; environmental; final engineering/design; plans, specifications, and estimates; and construction documents for the reconstruction and widening of sidewalks with the installation of pedestrian street lights, and the reconstruction/upgrade of the crosswalks and associated traffic signal infrastructure on Camp Wisdom Road from US 67 to Westmoreland Road in the city of Dallas for CSJ 0918-47-368 by Resolution No. 25-0122.

 

At this time, it is necessary to amend the Advance Funding Agreement with TxDOT to delete Attachment B, Project Budget, in its entirety and replace it with Attachment B-1, Project Budget, which revises the indirect state cost calculation formula, adds Category 7, Surface Transportation Block Grant (STBG) funds, and reduces Category 5, Congestion Mitigation and Air Quality (CMAQ) funds.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                           February 2025

Complete Design                                          February 2027

Begin Construction                                           April 2027

Complete Construction                     April 2029

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On March 8, 2023, the City Council authorized the acceptance of a grant from the United States Department of Transportation Federal Highway Administration through the Texas Department of Transportation (TxDOT) for the Congestion Mitigation and Air Quality Improvement Program (Agreement No. CSJ 0918-47-368, CFDA No. 20.205) as Federal share in the total project cost of $7,854,750.00 which includes $6,000,000.00 as Federal participation, $354,750.00 as State participation for indirect state cost, and $1,500,000.00 ($1,470,000.00 for design and construction and $30,000.00 for direct state cost paid to TxDOT prior to construction) as local participation for cost related to the reconstruction and widening of sidewalks with the installation of pedestrian street lights and the reconstruction/upgrade of the crosswalks and associated traffic signal infrastructure on West Camp Wisdom Road from U.S. 67 to South Westmoreland Road in Dallas County by Resolution No. 23-0369.

 

On January 8, 2025, the City Council authorized a professional engineering services contract with Gresham Smith, most highly qualified proposer of four, to develop preliminary engineering; environmental; final engineering/design; plans, specifications, and estimates; and construction documents for the reconstruction and widening of sidewalks with the installation of pedestrian street lights, and the reconstruction/upgrade of the crosswalks and associated traffic signal infrastructure on Camp Wisdom Road from US 67 to Westmoreland Road in in the city of Dallas for CSJ No. 0918-47-368 by Resolution No. 25-0122.

 

 

FISCAL INFORMATION

 

This action has no cost consideration to the City.

 

*Note - the increase and decrease in the amounts as outlined in Attachment B-1 of the amendment to the AFA does not change the total amount of the grant. The changes are as follows:

 

•                     Construction Cat. 5 (CMAQ) decreased from $6,860,000.00 to $3,110,000.00

•                     Construction Cat. 7 (STBG) increased from $0.00 to $3,750,000.00

•                     Indirect State Cost decreased from $354,750.00 to $7,095.00 (does not affect the grant amount to the City)

 