File #: 24-900    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 2/29/2024 In control: Department of Transportation
On agenda: 4/10/2024 Final action:
Title: Authorize Amendment No. 1 to the Advance Funding Agreement (Agreement No. CSJ 0918-47-374, Assistance Listing No. 20.205) between the City of Dallas and the Texas Department of Transportation for the reconstruction and upgrade of signals/equipment and construction of pedestrian improvements at seven intersections along Lemmon Avenue to (1) add the location of Lemmon Avenue at Wycliff Avenue; (2) remove the location of Lemmon Avenue at North Central Expressway (US 75); and (3) revise the location map - Financing: No cost consideration to the City
Indexes: 13, 14, 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     April 10, 2024

COUNCIL DISTRICT(S):                     2, 13, 14

DEPARTMENT:                     Department of Transportation

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize Amendment No. 1 to the Advance Funding Agreement (Agreement No. CSJ 0918-47-374, Assistance Listing No. 20.205) between the City of Dallas and the Texas Department of Transportation for the reconstruction and upgrade of signals/equipment and construction of pedestrian improvements at seven intersections along Lemmon Avenue to (1) add the location of Lemmon Avenue at Wycliff Avenue; (2) remove the location of Lemmon Avenue at North Central Expressway (US 75); and (3) revise the location map - Financing: No cost consideration to the City

 

Body

BACKGROUND

 

The City of Dallas and the Texas Department of Transportation (TxDOT) executed a contract on March 21, 2023, to effectuate their agreement for the reconstruction and upgrade of signals/equipment and construction of pedestrian improvements at the following seven intersections: Lemmon Avenue and Manor Way; Lemmon Avenue and Haggar Way; Lemmon Avenue and Inwood Road; Lemmon Avenue and Hudnall Street; Lemmon Avenue and Lomo Alto Drive; Lemmon Avenue and Turtle Creek Boulevard; and Lemmon Avenue and North Central Expressway (US 75).

 

The agreement inadvertently included the intersection of Lemmon Avenue and North Central Expressway (US 75) and excluded the intersection of Lemmon Avenue and Wycliff Avenue. The traffic signal upgrade at Lemmon Avenue and North Central Expressway (US 75) is being implemented by TxDOT through a different funding program, deeming it necessary to amend the agreement to revise the project locations.

 

If approved, this action will authorize an amendment to the agreement to add the location of Lemmon Avenue at Wycliff Avenue, to remove the location of Lemmon Avenue at North Central Expressway (US 75), and to revise the location map to reflect the changes.

 

Attachment A, Location Map Showing Project, is deleted in its entirety and replaced with Attachment A-1, Location Map Showing Project, which is attached to and made part of this amendment.

 

All other provisions of the original contract are unchanged and remain in full force and effect.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                                                                    November 2022

Revised Complete Design                                                               June 2024

Revised Begin Construction                                           January 2025

Revised Complete Construction                                          February 2026

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On January 25, 2023, the City Council authorized an Advance Funding Agreement with TxDOT to accept a federal Congestion Mitigation and Air Quality Improvement Program grant in the amount of $2,000,000.00 as federal share in the total project cost of $2,619,446.00 (Federal share $2,000,000.00, Indirect State $94,446.00, and City of Dallas participation $525,000.00 of which $30,000.00 is to be paid to TxDOT prior to construction) for the reconstruction and upgrade of signals/equipment and construction of pedestrian improvements at the following seven intersections: Lemmon Avenue and Manor Way; Lemmon Avenue and Haggar Way; Lemmon Avenue and Inwood Road; Lemmon Avenue and Hudnall Street; Lemmon Avenue and Lomo Alto Drive; Lemmon Avenue and Turtle Creek Boulevard; and Lemmon Avenue and North Central Expressway (US 75) by Resolution No. 23-0180.

 

FISCAL INFORMATION

 

No cost consideration to the City.


MAP

 

Attached