PILLAR: Sustainable
AGENDA DATE: April 8, 2026
COUNCIL DISTRICT(S): 6
DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize a professional services contract with Consor North America, Inc. dba Consor Engineers, to provide engineering services for the design of Irving Boulevard State Highway 356 Bridge over Elm Fork of Trinity River - Not to exceed: $1,235,211.50 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund)
*In alignment with Infrastructure Management Plan.
Body
BACKGROUND
The Request for Qualifications (CIZ24-PBW-3124) was issued on October 9, 2024, for Streets and Transportation Design Services for Special Projects; and the Request for Proposals was issued on April 11, 2025 for Irving Boulevard (Blvd.) State Highway 356 (SH356) Bridge over Elm Fork of Trinity River. Consor North America, Inc. dba Consor Engineers, was selected following a qualifications-based selection process in accordance with the City of Dallas procurement guidelines.
The City is planning to rehabilitate the existing Irving Blvd. SH356 Bridge. The bridge is located over and near the Trinity View Soccer Fields and the Trinity Parkway Campion Trail. The project will involve removing and replacing current bridge deck, railings, lighting, and approaches. The work will also include rehabilitating existing beams and substructure as necessary, inspecting and repairing substructure and other bridge elements if required. The scope will also cover traffic control plan options and associated costs, engineering services during construction, environmental services, a construction schedule, and an engineer’s estimate for construction.
This action will authorize a professional services contract with Consor North America, Inc., dba Consor Engineers, to provide engineering services for the design of Irving Blvd. SH356 Bridge over Elm Fork of Trinity River, in an amount not to exceed $1,235,211.50.
ESTIMATED SCHEDULE OF PROJECT
Begin Design April 2026
Complete Design March 2030
Begin Construction January 2028
Complete Construction March 2030
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
|
Fund |
FY 2026 |
FY 2027 |
Future Years |
|
Street and Transportation (A) Fund (2024 General Obligation Bond Fund) |
$1,235,211.50 |
$0.00 |
$0.00 |
LOCAL PARTICIPATION
|
Prime |
Status |
Workforce % |
|
Consor North America, Inc., dba Consor Engineers |
Local |
11.54% |
OWNER/EXECUTIVE
Consor North America, Inc., dba Consor Engineers
SriKrishna Peapully, P.E., Executive Vice President
MAP
Attached