Legislation Details

File #: 26-1353A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 4/13/2026 In control: Dallas Water Utilities Department
On agenda: 5/27/2026 Final action:
Title: Authorize an increase in the construction services contract with Rebcon, LLC for additional work associated with the Bachman Dam and Spillway Improvement Project - Not to exceed $809,519.08, from $44,196,556.72 to $45,006,075.80 - Financing: Water Capital Improvement F Fund ($550,847.72) and Water Construction Fund ($258,671.36) *In alignment with Water and Wastewater Capital Improvement Program.
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     May 27, 2026

COUNCIL DISTRICT(S):                     6

DEPARTMENT:                     Dallas Water Utilities Department

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Rebcon, LLC for additional work associated with the Bachman Dam and Spillway Improvement Project - Not to exceed $809,519.08, from $44,196,556.72 to $45,006,075.80 - Financing: Water Capital Improvement F Fund ($550,847.72) and Water Construction Fund ($258,671.36)

 

*In alignment with Water and Wastewater Capital Improvement Program.

 

Body

BACKGROUND

 

On September 27, 2023, the City Council authorized a construction services contract for the Bachman Dam and Spillway Improvement Project with Rebcon, LLC. The project included the rehabilitation of the Bachman dam and spillway to address regulatory flood capacity as well as structural and stability recommendations, replacement of the railroad bridge that spans the spillway, and trail improvements along the top of the dam. These improvements ensure dam safety and regulatory compliance, minimize flood risk, and allow residents to enjoy the lake for years to come.

 

During the course of construction, additional work outside the scope of the original contract has been required. An increase to the contract was authorized on October 22, 2025, to remove and replace unsuitable subgrade materials, clear vegetation downstream of the spillway, complete concrete placement and slope repairs, adjust the trail alignment on the northside of the dam to eliminate the need to remove trees, add rock riprap and articulated concrete blocks for slope protection, modify electrical work, remove debris from the face of the dam beyond the limits of the project, and make additional pipeline and pavement repairs in the area of construction.

 

 

 

 

 

 

The project has now been completed, and in order to close out the project, it is necessary to process a final increase to the contract for additional work performed by the contractor. The additional work includes railroad crossing improvements at the south trail tie-in, construction and repair modifications for railroad bridge retaining walls, spillway abutment modifications, trail adjustments at the dock area, rail replacement and track repairs, fiberglass reinforced plastic  repairs, installation of bar grating around abutments, addition of handrails, lighted gates, bollards, and buoys, and replacement of the fishing hole lake grate. These items were necessary during construction to ensure safety, functionality, and the successful execution of the project.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                                          November 2023

Complete Construction                     May 2026

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 27, 2023, the City Council authorized a construction services contract with Rebcon, LLC, Inc. for the Bachman Dam and Spillway Improvement Project by Resolution No. 23-1357.

 

On October 22, 2025, the City Council authorized an increase in the construction services contract with Rebcon, LLC for additional work associated with the Bachman Dam and Spillway Improvement Project by Resolution No. 25-1663.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

Water Capital Improvement F Fund

$550,847.72

$0.00

$0.00

Water Construction Fund

$258,671.36

$0.00

$0.00

Total

$809,519.08

$0.00

$0.00

 

Construction Contract                                                               $43,179,000.00

Change Order No. 1                     $  1,017,556.72

Change Order No. 2 (this action)                                          $     809,519.08

 

Total Project Cost                                                                                    $45,006,075.80

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Rebcon, LLC

Non-local

32.32%

 

OWNER/EXECUTIVE

 

Rebcon, LLC

 

Daniel Krieg, President

 

MAP

 

Attached