PILLAR: Sustainable
AGENDA DATE: February 11, 2026
COUNCIL DISTRICT(S): 3
DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with Ed Bell Construction Company for the relocation of an existing 12-inch water main needed on Camp Wisdom Road from Farm-to-Market (FM) 1382 to Mountain Creek Parkway - Not to exceed $359,413.28, from $6,924,105.95 to $7,283,519.23 - Financing: Water Capital Improvement G Fund
*In alignment with Infrastructure Management Plan.
Body
BACKGROUND
On September 27, 2023, the City Council authorized the construction services contract with Ed Bell Construction Company for the construction of a thoroughfare improvement project on Camp Wisdom Road from FM 1382 to Mountain Creek Parkway by Resolution No. 23-1323.
During construction it was determined that the proposed culvert extension is too close to the existing 12-inch water main. It was determined that the best solution would be to relocate the existing water main above the proposed culvert and below the shared-use path.
This action will authorize Change Order No. 2 in the construction services contract with Ed Bell Construction Company for the relocation of an existing 12-inch water main needed on Camp Wisdom Road from FM 1382 to Mountain Creek Parkway, in an amount not to exceed $359,413.28, increasing the contract from $6,924,105.95 to $7,283,519.23.
ESTIMATED SCHEDULE OF PROJECT
Began Construction March 2024
Complete Construction July 2026
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On September 27, 2023, the City Council authorized the construction services contract with Ed Bell Construction Company for the construction of a thoroughfare improvement project on Camp Wisdom Road from FM 1382 to Mountain Creek Parkway by Resolution No. 23-1323.
FISCAL INFORMATION
|
Fund |
FY 2026 |
FY 2027 |
Future Years |
|
Water Capital Improvement G Fund |
$359,413.28 |
$0.00 |
$0.00 |
Construction Contract $6,855,180.45
Change Order No.1 $ 68,925.50
Change Order No. 2 (this action) $ 359,413.28
Total $7,283,519.23
LOCAL PARTICIPATION
|
Prime |
Status |
Workforce % |
|
Ed Bell Construction Company |
Local |
23.02% |
OWNER/EXECUTIVE
Ed Bell Construction Company
10605 Harry Hines Boulevard
Dallas, Texas 75220
William Douglas Teter, Vice President
MAP
Attached