File #: 25-2695A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 9/2/2025 In control: Department of Transportation and Public Works
On agenda: 10/22/2025 Final action:
Title: Authorize Amendment No. 2 to the Advance Funding Agreement (CSJ No. 0918-47-237, Assistant Listing No. 20.205) between the City of Dallas and the Texas Department of Transportation for the East Wheatland Road Extension Project to (1) replace Attachment C-1 with Attachment C-2, Project Budget, and to (2) amend the funding participation, increasing the total estimated cost by $10,278,893.00, from $4,445,390.00 to $14,724,283.00, the federal participation by $7,768,000.00, from $3,400,000.00 to $11,168,000.00, the indirect state cost by $433,543.00, from $191,140.00 to $624,683.00, and the local participation by $2,077,350.00, from $854,250.00 to $2,931,600.00 - Financing: No cost consideration to the City *In alignment with Infrastructure Improvements.
Indexes: 8
Attachments: 1. Map, 2. Resolution, 3. Attachment C-1, 4. Attachment C-2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     October 22, 2025

COUNCIL DISTRICT(S):                     8

DEPARTMENT:                     Department of Transportation and Public Works

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize Amendment No. 2 to the Advance Funding Agreement (CSJ No. 0918-47-237, Assistant Listing No. 20.205) between the City of Dallas and the Texas Department of Transportation for the East Wheatland Road Extension Project to (1) replace Attachment C-1 with Attachment C-2, Project Budget, and to (2) amend the funding participation, increasing the total estimated cost by $10,278,893.00, from $4,445,390.00 to $14,724,283.00, the federal participation by $7,768,000.00, from $3,400,000.00 to $11,168,000.00, the indirect state cost by $433,543.00, from $191,140.00 to $624,683.00, and the local participation by $2,077,350.00, from $854,250.00 to $2,931,600.00 - Financing: No cost consideration to the City

 

*In alignment with Infrastructure Improvements.

 

Body

BACKGROUND

 

The East Wheatland Road Extension Project (from Dallas/Lancaster city limits to University Hills Boulevard) is a partnership project between the City of Dallas and Texas Department of Transportation (TxDOT). The City of Dallas is the lead agency to administer the design and construction of the project.

 

The East Wheatland Road Extension Project (from Dallas/Lancaster city limits to University Hills Boulevard) will include the construction of a new four-lane undivided roadway with reinforced concrete pavement, curb, gutter, bicycle and pedestrian facilities, intersection reconstruction, water, storm drainage, a new bridge, culvert and street lighting.

 

Through the funding partnership with NCTCOG, the City of Dallas will provide funding for the Haskell Left Turn Project (CR No. 25-656A dated March 26, 2025) and cover the cost overruns for the Zaragoza Elementary Safe Routes to School (SRTS) project and the Elam Road SRTS project, in the estimated amount of $2.5 million. In exchange, the NCTCOG will cover the funding gap for the construction of roadway and pedestrian improvements (this action).

 

 

This action will authorize Amendment No. 2 to the Advance Funding Agreement (CSJ No. 0918-47- 237, Assistant Listing No. 20.205) between the City of Dallas and the TxDOT for the East Wheatland Road Extension Project to (1) replace Attachment C-1 with Attachment C-2, Project Budget, which is attached to and to (2) amend the funding participation, increasing the total estimated cost by $10,278,893.00, from $4,445,390.00 to $14,724,283.00, the federal participation by $7,768,000.00, from $3,400,000.00 to $11,168,000.00, the indirect state cost by $433,543.00, from $191,140.00 to $624,683.00, and the local participation by $2,077,350.00, from $854,250.00 to $2,931,600.00.

 

All other provisions of the original contract are unchanged and remain in full force and effect.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                  July 2019

Completed Design           September 2025

Begin Construction          May 2026

Complete Construction    August 2028

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On October 12, 2017, the Regional Transportation Council approved over $43.5 million in federal funding for the City of Dallas' proposed 2017 Bond Program Projects.

 

On January 27, 2021, the City Council authorized an Advance Funding Agreement with the TxDOT (CSJ No. 0918-47-237) and payment to TxDOT for engineering review and construction administration services for the design and construction of a new roadway on Wheatland Road from the city limits to University Hills Boulevard by Resolution No. 21-0219.

 

FISCAL INFORMATION

 

This action has no cost consideration to the City. Agenda items will be brought to the City Council for future projects

 

Project Funding:

Federal Participation                                           $11,168,000.00

Indirect State Cost                                                                $     624,683.00

City of Dallas                                                                $  2,931,600.00

 

Total Funding                                                                $14,724,283.00

 

MAP

 

Attached