PILLAR: Growing
AGENDA DATE: December 9, 2026
COUNCIL DISTRICT(S): 6
DEPARTMENT: Department of Aviation
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize (1) an architectural services contract with Brown Reynolds Watford Architects, Inc. to provide professional design and construction administration services for the Building B Rehabilitation and Renovation Project in support of the Love Field Expansion Airport Program; and (2) increase appropriations in an amount not to exceed $1,058,570.00 in the AVI Commercial Paper Fund - Not to exceed $1,058,570.00 - Financing: AVI Commercial Paper Fund
*In alignment with Love Field Expansion Airport Program (LEAP) .
Body
BACKGROUND
The Building B Rehabilitation and Renovation Project is an enabling project supporting the Love Field Expansion Airport Program (LEAP). LEAP is a multi-year capital improvement program that will transform Dallas Love Field (DAL) through significant investments in terminal, airside, landside, and support facility infrastructure. As LEAP progresses, Building B will serve as a modernized administrative and operational support facility to accommodate Department of Aviation personnel, consultants, and other project support personnel necessary to support the successful implementation of LEAP and ongoing airport operations while extending the useful life of the building
The project will modernize the existing airport support facility through selective demolition, interior renovations, building systems upgrades, façade improvements, site beautification, parking lot drainage and striping, sustainability enhancements, and construction administration. The project will result in a modern and efficient workplace designed to accommodate approximately 70 personnel while enhancing operational efficiency and sustainable building performance consistent with City of Dallas standards.
This action will authorize an architectural services contract with Brown Reynolds Watford Architects, Inc. to provide professional design and construction administration services for the Building B Rehabilitation and Renovation Project in support of the Love Field Expansion Airport Program.
ESTIMATED SCHEDULE OF PROJECT
Begin Design January 2027
Complete Design June 2027
Begin Construction October 2027
Complete Construction May 2028
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
|
Fund |
FY 2027 |
FY 2028 |
Future Years |
|
AVI Commercial Paper Fund |
$758,570.00 |
$300,000.00 |
$0.00 |
LOCAL PARTICIPATION
|
Prime |
Status |
Workforce % |
|
Brown Reynolds Watford Architects |
Local |
26.71% |
The following five proposals were received and opened on September 11, 2026:
*Denotes successful proposer
Proposers Bid Rank
*Brown Reynolds Watford Architects, Inc. 87.00%
3535 Travis Street
Suite 250
Dallas, TX 75204
Corgan 85.33%
Farnsworth Group 80.33%
RS&H 78.00%
GSR Andrade Architects 77.67%
OWNER/EXECUTIVE
Brown Reynolds Watford Architects, Inc.
Frederic Clifford, Principal-in-Charge