File #: 19-1992    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/5/2019 In control: Park & Recreation Department
On agenda: 1/8/2020 Final action: 1/8/2020
Title: Authorize a contract for the construction of the addition of a senior activity center, technology center, and gymnasium and expansion of the parking lot at Willie B. Johnson Recreation Center located at 12225 Willowdell Drive - J.C. Commercial, Inc., best value proposer of eight - Not to exceed $7,199,777.00 - Financing: Park and Recreation Facilities (B) Fund (2017 Bond Funds)
Indexes: 10
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life

AGENDA DATE:                     January 8, 2020

COUNCIL DISTRICT(S):                     10

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

 

Title

Authorize a contract for the construction of the addition of a senior activity center, technology center, and gymnasium and expansion of the parking lot at Willie B. Johnson Recreation Center located at 12225 Willowdell Drive - J.C. Commercial, Inc., best value proposer of eight - Not to exceed $7,199,777.00 - Financing: Park and Recreation Facilities (B) Fund (2017 Bond Funds)

 

Body

BACKGROUND

 

On August 24, 2019 and August 30, 2019, the City of Dallas advertised a Request for Competitive Sealed Proposals (RFCSP) for the construction of the addition of a senior activity center, technology center, and gymnasium and expansion of the parking lot at Willie B. Johnson Recreation Center located at 12225 Willowdell Drive.

 

Proposals based on RFCSP procurement process are evaluated on pre-set criteria which include cost, qualifications of the prime contractor, subcontractor experience, construction amount and schedule ratings, which are based on mathematical formulas, with the best price and best schedule being given the highest scores.  Ratings "1" to "10" are given for each criterion with "10" being the best rating.  These ratings are multiplied by the weighting to obtain the score for each criterion.

 

Following is a list of the rating criteria and values for each criterion:

 

Rating Criteria                     Value

 

1. Proposed Construction Contract Amount                        45%

2. Qualifications/Experience/References for Prime Firm                       20%

3. Subcontractor Experience                       10%

4. Business Inclusion and Development Plan                       15%

5. Financial Sufficiency                         5%

6. Proposed Schedule/Time of Completion                         5%

                     100%

 

The selection committee scored the proposals and J.C. Commercial, Inc., was selected as the best value proposer.

 

This action will authorize a contract with J.C. Commercial, Inc., best value proposer of eight, for the construction of the addition of a senior activity center, technology center, and gymnasium and expansion of the parking lot at Willie B. Johnson Recreation Center located at 12225 Willowdell Drive, including the Base Bid and Alternate No. 1, in an amount not to exceed $7,199,777.00.

 

The scope of work includes the construction of a new senior center with a dedicated reception area, restrooms, multi-purpose room, game room, learning kitchen and storage; a technology center; and a gymnasium with basketball court, restrooms and a walking track.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     January 2020

Complete Construction                     January 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On December 12, 2019, the Park and Recreation Board authorized a contract with J.C. Commercial, Inc. for the construction of the addition of a senior activity center, technology center, and gymnasium and expansion of the parking lot at Willie B. Johnson Recreation Center located at 12225 Willowdell Drive.

 

FISCAL INFORMATION

 

Park and Recreation Facilities (B) Fund (2017 Bond Funds) - $7,199,777.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$7,199,777.00

Construction

25.00%

27.01%

$1,944,576.40

This contract exceeds the M/WBE goal.

 

PROCUREMENT INFORMATION

 

The following eight proposals were received and opened on September 27, 2019:

 

*Denotes successful proposer

 

 

 

Proposers                     Base Bid                     Alt. No. 1**                     Total Bid                     Rank

 

*J.C. Commercial, Inc.                     $7,187,777.00                     $12,000.00                     $7,199,777.00                     1

 1801 Lakepointe Dr. #129

 Lewisville, TX 75057

Big Sky Construction                     $7,425,000.00                     $90,000.00                     $7,515,000.00                     2

 Company, Inc.

DENCO CS Corporation                     $6,775,525.00                     $         0.00                     $6,775,525.00                     3

Northridge Construction                     $7,557,984.00                     $80,000.00                     $7,637,984.00                     4

 Group, LLC

MDI General Contractors                     $7,804,000.00                     $         0.00                     $7,804,000.00                     5

Con-Real, LP.                     $8,336,982.22                     $         0.00                     $8,336,982.22                     6

Phillips/May Corporation                     $7,989,333.00                     $         0.00                     $7,989,333.00                     7

Azteca Enterprises, Inc.                     $8,312,600.00                     $         0.00                     $8,312,600.00                     8

 

**Alternate No. 1 - provides for adding sound isolation in Studios 302A and 302B at the technology center.

 

Note: After value engineering, the best and final offer from J.C. Commercial, Inc. was $7,199,777.00.

 

OWNER

 

J.C. Commercial, Inc.

 

Larry Wagnor, President

 

MAP

 

Attached