File #: 24-2282    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved as an Individual Item
File created: 7/22/2024 In control: Water Utilities Department
On agenda: 8/28/2024 Final action:
Title: Authorize an increase in the construction services contract with Archer Western Construction, LLC, for additional work associated with Dallas Water Utilities' raw water system facilities located at Lake Ray Hubbard - Not to exceed $993,520.00, from $32,082,400.00 to $33,075,920.00 - Financing: Water Construction Fund
Indexes: 9
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     August 28, 2024

COUNCIL DISTRICT(S):                     9

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Archer Western Construction, LLC, for additional work associated with Dallas Water Utilities’ raw water system facilities located at Lake Ray Hubbard - Not to exceed $993,520.00, from $32,082,400.00 to $33,075,920.00 - Financing: Water Construction Fund

 

Body

BACKGROUND

 

Dallas Water Utilities (DWU) identified and evaluated 10 raw water facilities based on their age and condition, impact to the system, reliability, cost to operate, and frequency of repairs. The most critical raw water facilities were found to include the lake intake, Forney Pump Station, and Forney Dam at Lake Ray Hubbard. Lake Ray Hubbard is the only DWU reservoir owned and operated by the City of Dallas. The reservoir and associated water supply infrastructure were constructed in the late 1960’s and early 1970’s and several critical components require rehabilitation and replacement.

 

On August 10, 2022, the City Council authorized a construction services contract with Archer Western Construction, LLC for major rehabilitation and replacement of infrastructure at Lake Ray Hubbard. Improvements include traveling screens, sluice gate replacement at the intake, pump and valve replacement, site civil and groundwater monitoring improvements, monorail and bridge crane system improvements, new stop logs and storage building, spillway concrete repairs, spillway gate repairs, heating, ventilation, and air conditioning upgrades, and electrical and control improvements for the Forney Dam. The existing facilities have reached the end of their useful life, have limited operability, and are difficult to access and repair.

 

 

 

 

 

 

 

 

This action will authorize Change Order No.1 to the construction services contract with Archer Western Construction, LLC for additional work associated with the rehabilitation and replacement of infrastructure at Lake Ray Hubbard. During construction, additional work not within the original contract was identified and is required to complete the proposed improvements. The additional work includes repair of the tainter gates and inspection of the low flow West slide gates, services for the crane rail design, replacement of one 60-inch butterfly valve, meter flow vault, replacement of two pressure relief/pressure sustaining surge control valves, and installation of new doors and hardware at the Forney Pump Station electrical building and bulkhead storage building.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                                                               October 2022

Complete Construction                                                               November 2025

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 10, 2022, the City Council authorized a construction services contract with Archer Western Construction, LLC for major maintenance and rehabilitation improvements at Dallas Water Utilities’ raw water system facilities located at Lake Ray Hubbard, by Resolution No. 22-1131.

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Water Construction Fund

$993,520.00

$0.00

$0.00

 

Construction                                                                                                         $32,082,400.00

Change Order No. 1 (this action)                                          $     993,520.00

 

Total Project Cost                                                                                    $33,075,920.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$993,520.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

7.15%

7.15%

$71,085.73

This contract does not meet the M/WBE subcontracting goal.

Archer Western Construction, LLC - Local; Workforce - 7.15% Local

 

 

OWNER

 

Archer Western Construction, LLC

 

Daniel P. Walsh, President

 