Skip to main content
Dallas Logo
File #: 25-1273A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 4/4/2025 In control: Dallas Water Utilities Department
On agenda: 5/28/2025 Final action:
Title: Authorize Supplemental Agreement No. 2 to the professional services contract with Gresham Smith, for additional engineering services associated with the Lower East Bank Interceptor - Not to exceed $1,537,899.00, from $2,527,984.50 to $4,065,883.50 - Financing: Wastewater Capital Improvement G Fund
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     May 28, 2025

COUNCIL DISTRICT(S):                     6

DEPARTMENT:                     Dallas Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize Supplemental Agreement No. 2 to the professional services contract with Gresham Smith, for additional engineering services associated with the Lower East Bank Interceptor - Not to exceed $1,537,899.00, from $2,527,984.50 to $4,065,883.50 - Financing: Wastewater Capital Improvement G Fund

 

Body

BACKGROUND

 

On December 14, 2016, the City Council awarded a professional services contract to Gresham Smith for the engineering design and surveying of an estimated 36,138 feet of water and wastewater main replacements at 13 locations. One of those locations included the replacement and rehabilitation of the existing Lower East Bank wastewater interceptor system that is in poor structural condition and needs additional capacity to support ongoing and future development. The Lower East Bank Interceptor has been identified in master planning efforts as one of Dallas Water Utilities’ Department (DWU) most critical pipeline improvement projects.

 

Following the completion of design and prior to the advertisement for construction bids, DWU completed an updated master plan that recommended an increase to the wastewater flows to be conveyed by the Lower East Bank Interceptor. The increased flows required the Lower East Bank Interceptor design to be modified before advertising for construction bids. On September 23, 2020, a construction contract was awarded and following award of the contract it was determined that the bottom of an existing pressure storm sewer conflicted with the proposed alignment of the interceptor. The existing pressure sewer has a bottom elevation different than what was originally anticipated based on the best available records and a portion of the interceptor design was modified to clear the conflict.

 

 

 

 

 

On November 9, 2022, the City Council authorized Supplemental Agreement No. 1 to the professional services contract with Gresham Smith, for additional engineering services necessary to complete the Lower East Bank Interceptor Project. Supplemental Agreement No. 1 funded the previous design modifications and allowed for the remaining funds to be used for construction phase services. During construction, several utility conflicts and constructability issues were encountered. Despite efforts to clear these conflicts and issues it was determined that the scope of the construction contract would need to be reduced and that additional engineering services need to be completed. Following completion of these additional engineering services, DWU will repackage the remaining work not completed by the original construction contract and advertise for new construction bids.

     

This action will authorize Supplemental Agreement No. 2 to the professional services contract with Gresham Smith for additional engineering services necessary to revise the design and repackage the remaining work for construction. The additional services include geotechnical explorations and evaluations, a Geotechnical Baseline Report, updating the design based on the new geotechnical information, environmental services, procuring the remaining construction work using Competitive Sealed Proposals, and additional construction phase services. 

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Additional Services               May 2025

Complete Additional Services        March 2029

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On December 14, 2016, the City Council authorized engineering services contracts with four consulting firms to provide design services for the replacement and rehabilitation of water and wastewater mains at 109 locations - Huitt-Zollars, Inc., APM & Associates, Inc., Gresham Smith and Partners, and Burgess & Niple, Inc., by Resolution No. 16-1946.

 

On November 9, 2022, the City Council authorized Supplemental Agreement No. 1 to the professional services contract with Gresham Smith to provide additional engineering services for the Lower East Bank Interceptor, by Resolution No. 22-1700.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Wastewater Capital Improvement G Fund

$1,537,899.00

$0.00

$0.00

 

Original Contract                                                            $2,180,474.50

Supplemental Agreement No. 1                                     $   347,510.00

Supplemental Agreement No. 2 (this action)                     $1,537,899.00

                                                                                   

Total Contract                                                                 $4,065,883.50

 

 

 

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$1,537,899.00

Architecture & Engineering

34.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

61.02%

61.02%

$938,435.00

This contract exceeds the M/WBE goal.

Gresham Smith, Inc.- Local; Workforce - 43.18% Local

 

OWNER/EXECUTIVE

 

Gresham Smith

 

Chris Kaakaty, Senior Vice President

 

MAP

 

Attached