File #: 23-55    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved as an Individual Item
File created: 10/19/2022 In control: Water Utilities Department
On agenda: 2/22/2023 Final action:
Title: Authorize a construction services contract for roof replacements and minor building repairs at Dallas Water Utilities owned facilities (list attached to the Agenda Information Sheet) - Gadberry Construction Company, Inc., lowest responsible bidder - Not to exceed $9,359,000.00 - Financing: Water Construction Fund ($6,173,679.00), Wastewater Capital Improvement G Fund ($2,769,321.00), and Storm Drainage Management Capital Construction Fund ($416,000.00)
Indexes: 10, 2, 200, 3, 4, 6, 7, 8
Attachments: 1. List, 2. Map, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     February 22, 2023

COUNCIL DISTRICT(S):                     2, 3, 4, 6, 8, 10, Outside City Limits

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for roof replacements and minor building repairs at Dallas Water Utilities owned facilities (list attached to the Agenda Information Sheet) - Gadberry Construction Company, Inc., lowest responsible bidder - Not to exceed $9,359,000.00 - Financing:  Water Construction Fund ($6,173,679.00), Wastewater Capital Improvement G Fund ($2,769,321.00), and Storm Drainage Management Capital Construction Fund ($416,000.00)

 

Body

BACKGROUND

 

Dallas Water Utilities (DWU) utilizes 270 structures with approximately 1.7 million square feet of roof systems that have an estimated replacement value of $20,400,000. DWU facilities are generally exposed to more aggressive and corrosive environments due to chemicals used in some of the treatment processes. With this exposure, roof materials break down at a higher rate, necessitating frequent repair and maintenance to properly manage these assets.

 

In 2019, a roof assessment was performed on all DWU buildings by Terracon Consultants, Inc. Working with Terracon, DWU established a priority ranking for replacing roofs based on age and wear. This contract is Priority 1 roofs that have reached the end of their life and Priority 2 - one to two years of expected life left.

 

This action will authorize a construction services contract for work associated with roof replacements at 46 buildings and minor renovations of windows and parapets at the Elm Fork and Eastside Water Treatment plants. The proposed work was prioritized based on roof and structure assessments and packaged for replacement and renovation under this contract. Regularly scheduled roof replacements and repairs along with minor renovations protect critical building assets and ensure continued reliable water, wastewater, and stormwater service to approximately 2.5 million customers.

 

 

 

 

 

The following chart illustrates Gadberry Construction Company, Inc.’s contractual activities with the City of Dallas for the past three years:

 

                     PBW                     DWU                     PKR                     TRN

 

Projects Completed                     0                     0                     0                     0

Active Projects                     0                     1                     0                     0

Change Orders                     0                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          March 2023

Complete Construction                     July 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2023

FY 2024

Future Years

Water Construction Fund

$6,173,679.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$2,769,321.00

$0.00

$0.00

Storm Drainage Management Capital Construction Fund

$   416,000.00

$0.00

$0.00

Total

$9,359,000.00

$0.00

$0.00

 

          Council District                                 Amount

 

                      2                                       $   193,600.00

                      3                                       $   566,600.00

                      4                                       $3,316,200.00

                      6                                       $   778,600.00

                      8                                       $1,008,600.00

                      10                                     $   459,600.00

         Outside City Limits                        $3,035,800.00

 

                      Total                                 $9,359,000.00

 

 

 

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$9,359,000.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

6.02%

34.77%

$3,253,825.00

This contract exceeds the M/WBE goal.

This contract did not meet the M/WBE goal, however, the overall M/WBE participation was met.

Gadberry Construction Company, Inc- Local; Workforce - 15.80% Local

 

PROCUREMENT INFORMATION

 

The following bids with quotes were received and opened on October 14, 2022:

 

*Denotes successful bidder

 

Bidders                     Bid Amount

 

*Gadberry Construction Company, Inc.                     $  9,359,000.00

 1312 Conant Street

 Dallas, Texas 75207

Texas Roof Management, Inc.                     $10,553,830.00

 

OWNER

 

Gadberry Construction Company, Inc.

Dustin Gadberry, President

 

MAP

 

Attached