File #: 20-1180    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 6/2/2020 In control: Water Utilities Department
On agenda: 8/12/2020 Final action: 8/12/2020
Title: Authorize (1) a Standard Utility Agreement with the State of Texas, acting through the Texas Department of Transportation, for water and wastewater main relocations and appurtenance adjustments in various locations near Interstate Highway 45 (Julius Schepps Freeway) and U.S. Highway 175 (S.M. Wright Freeway); and (2) the receipt and deposit of funds from the Texas Department of Transportation for the reimbursement of project management and construction inspection costs for the reimbursable portion of the project - Estimated Revenue: Dallas Water Utilities Fund $24,536.64
Indexes: 7
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     August 12, 2020

COUNCIL DISTRICT(S):                     7

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize (1) a Standard Utility Agreement with the State of Texas, acting through the Texas Department of Transportation, for water and wastewater main relocations and appurtenance adjustments in various locations near Interstate Highway 45 (Julius Schepps Freeway) and U.S. Highway 175 (S.M. Wright Freeway); and (2) the receipt and deposit of funds from the Texas Department of Transportation for the reimbursement of project management and construction inspection costs for the reimbursable portion of the project - Estimated Revenue: Dallas Water Utilities Fund $24,536.64

 

body

BACKGROUND

 

This project consists of constructing approximately 3,200 feet of water main ranging in size from 6 to 30 inches in diameter, 2,400 feet of 8-inch diameter wastewater main, and water and wastewater appurtenance adjustments in conjunction with paving and drainage improvements by the Texas Department of Transportation (TxDOT) in various location near Interstate Highway 45 and U.S. Highway 175. TxDOT has designed the paving, storm drainage facilities, and the water and wastewater main relocations and appurtenance adjustments. TxDOT has agreed to incorporate Dallas Water Utilities (DWU) water and wastewater main relocations and appurtenance adjustments into their construction contract and administer the project during construction.

Under the Standard Utility Agreement with the State of Texas, acting through TxDOT, TxDOT will reimburse DWU for the cost of staff salaries for project management and construction inspection required for the reimbursable portion of the project. TxDOT will be responsible for administering the construction of the water and wastewater main relocations and the appurtenance adjustments. TxDOT awarded the construction project in December 2019.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                                          May 2020

Complete Construction                     May 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 28, 2019, City Council authorized an Advance Funding Agreement with the State of Texas, acting through the Texas Department of Transportation, for construction of water and wastewater main relocations and appurtenance adjustments along S.M. Wright Freeway from U.S. Highway 175 (C.F. Hawn Freeway) to Interstate Highway 45 (Julius Schepps Freeway) by Resolution No. 19-1283.

 

FISCAL INFORMATION

 

Estimated Revenue: Dallas Water Utilities Fund $24,536.64

 

MAP

 

Attached