Skip to main content
Dallas Logo
File #: 25-471A    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 1/24/2025 In control: Department of Transportation and Public Works
On agenda: 2/26/2025 Final action:
Title: Authorize an increase to the construction services contract with HD Way Concrete Service, LLC for the additional water and wastewater main improvements needed for Street Reconstruction Group 17-4009 - Not to exceed $187,750.00, from $2,370,432.75 to $2,558,182.75 - Financing: Water Capital Improvement G Fund ($136,500.00), Wastewater Capital Improvement G Fund ($51,250.00)
Indexes: 4
Attachments: 1. Maps, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     February 26, 2025

COUNCIL DISTRICT(S):                     4

DEPARTMENT:                     Department of Transportation and Public Works

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase to the construction services contract with HD Way Concrete Service, LLC for the additional water and wastewater main improvements needed for Street Reconstruction Group 17-4009 - Not to exceed $187,750.00, from $2,370,432.75 to $2,558,182.75 - Financing: Water Capital Improvement G Fund ($136,500.00), Wastewater Capital Improvement G Fund ($51,250.00)

 

Body

BACKGROUND

 

On June 14, 2023, the City Council authorized the construction services contract with HD Way Concrete Service, LLC for the construction of Street Reconstruction Group 17-4009, by Resolution No. 23-0781.

 

During construction, it was discovered that in order to complete the proposed storm drainage construction on Montague Avenue, it was necessary to clear the conflicting water and wastewater main lines encountered. This will require adding the additional water and wastewater main improvements needed to the contract.

 

This action will authorize Change Order No. 5 to the construction services contract with HD Way Concrete Service, LLC for the additional water and wastewater main improvements needed for Street Reconstruction Group 17-4009.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction       October 2023

Complete Construction  July 2025

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On June 14, 2023, the City Council authorized a construction services contract with HD Way Concrete Service, LLC for the construction of Street Reconstruction Group 17-4009, by Resolution No. 23-0781.

 

On April 24, 2024, the City Council authorized Change Order No. 1 to the construction services contract with HD Way Concrete Service, LLC for the additional water adjustments and wastewater main improvements needed on Street Reconstruction Group 17-4009, by Resolution No. 24-0595.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Water Capital Improvement G Fund

$136,500.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$  51,250.00

$0.00

$0.00

Total

$187,750.00

$0.00

$0.00

 

Construction Contract                                                                                                         $  2,090,214.00

Change Order No. 1                                                                                                         $     163,375.00

Change Order No. 2                                                                                                         $                0.00

Change Order No. 3                                                                                                         $       99,843.75

Change Order No. 4                                                                                                         $       17,000.00

Change Order No. 5 (this action)                                                                                    $     187,750.00

 

Total                                                                                                                                                                        $  2,558,182.75

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$187,750.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

100.00%

100.00%

$187,750.00

This contract exceeds the M/WBE goal.

HD Way Concrete Service, LLC - Local; Workforce - 72.72% Local

 

OWNER/EXECUTIVE

 

HD Way Concrete Service, LLC

2760 Autumn Breeze

Grand Prairie, Texas 75052

 

David W. Bowers, President

 

 

 

MAPS

 

Attached