File #: 22-1378    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 6/2/2022 In control: Water Utilities Department
On agenda: 8/10/2022 Final action:
Title: Authorize an increase in the construction services contract with Douglas Dailey Construction, LLC for additional work associated with the installation of permitted wastewater services - Not to exceed $2,598,950.00, from $10,557,637.50 to $13,156,587.50 - Financing: Wastewater Construction Fund
Indexes: 100
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     August 10, 2022

COUNCIL DISTRICT(S):                     All

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Douglas Dailey Construction, LLC for additional work associated with the installation of permitted wastewater services - Not to exceed $2,598,950.00, from $10,557,637.50 to $13,156,587.50 - Financing: Wastewater Construction Fund

 

Body

BACKGROUND

 

On June 9, 2021, City Council authorized a construction services contract for (1) an eighteen-month master agreement for water and wastewater small services installations; (2) the installation of water and wastewater mains at four locations; (3) and an eighteen-month master agreement for water and wastewater mainline extensions and emergency mainline installations and relocations at various locations by Resolution No. 21-1024.

 

Following implementation of the contract, Dallas Water Utilities (DWU) has received a significantly higher than anticipated volume of permitted wastewater service line requests. The installation of these service lines support development activities and are initiated upon issuance of a permit to a property owner by Development Services. Available funding under the original contract will not be adequate to provide permitted wastewater service installations for the rest of the contract term.

 

This action will authorize additional funding to keep up with anticipated wastewater service installation requests for the remaining period of the contract. In order to avoid major disruption and delays to development efforts, it is critical to provide new wastewater service lines in a timely manner. The delay of permitted service line installations is likely to lead to excessive customer complaints and will affect DWU’s efforts to meet the needs of future growth.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                     September 2021

Complete Construction                     February 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On June 9, 2021, City Council authorized a construction services contract for (1) an eighteen-month master agreement for water and wastewater small services installations; (2) the installation of water and wastewater mains at four locations; and (3) an eighteen-month master agreement for water and wastewater mainline extensions and emergency mainline installations and relocations at various locations by Resolution No. 21-1024.

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Wastewater Construction Fund

$2,598,950.00

$0.00

$0.00

 

Construction                                                                                                         $10,557,637.50

Change Order No. 1 (this action)                                          $  2,598,950.00

 

Total Project Cost                                                                                    $13,156,587.50

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

M/WBE %

M/WBE $

$2,598,950.00

Construction

32.00%

36.39%

$945,781.00

This contract exceeds the M/WBE goal.

Change Order No.1 - 39.46% Overall Participation

Douglas Dailey Construction, LLC - Non-local; Workforce - 20.00% Local

 

OWNER

 

Douglas Dailey Construction, LLC

 

Douglas Dailey, President