Skip to main content
Dallas Logo
File #: 26-67A    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/23/2025 In control: Department of Transportation and Public Works
On agenda: 2/25/2026 Final action:
Title: Authorize an increase in the construction services contract with Rebcon, LLC for the additional water main improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue - Not to exceed $150,240.00, from $30,443,508.24 to $30,593,748.24 - Financing: Water Capital Improvement G Fund *In alignment with Infrastructure Improvements Plan.
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     February 25, 2026

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Transportation and Public Works

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Rebcon, LLC for the additional water main improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue - Not to exceed $150,240.00, from $30,443,508.24 to $30,593,748.24 - Financing: Water Capital Improvement G Fund

 

*In alignment with Infrastructure Improvements Plan.

 

Body

BACKGROUND

 

On September 27, 2023, the City Council authorized a construction services contract with Rebcon, LLC for the construction of Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 23-1324.

 

During construction, it was discovered that unknown substandard fire line connections existed within the project limits that needed to be replaced, which requires additional water services to bring the fire lines to standard. Consequently, it is necessary to add to the contract the additional water pipe, valves, vault, meters and water services needed to complete the fire line connections to the new water mainline.

 

This action will authorize Change Order No. 4 to the construction services contract with Rebcon, LLC for the additional water main improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue, in an amount not to exceed $150,240.00.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                                          April 2024

Complete Construction                     March 2027

 

 

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 27, 2023, the City Council authorized a construction services contract with Rebcon, LLC for the construction of Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 23-1324.

 

On February 26, 2025, the City Council authorized Change Order No. 2 to the construction services contract with Rebcon, LLC for the additional wastewater improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 25-0353.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

Water Capital Improvement G Fund

$150,240.00

$0.00

$0.00

 

Construction Contract                                                               $29,968,199.00

Change Order No. 1                                                                $       93,750.00

Change Order No. 2                                                                $     286,347.68

Change Order No. 3                                                                $       95,211.56

Change Order No. 4 (this action)                                          $     150,240.00

 

Total                                                                                                                               $30,593,748.24

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Rebcon, LLC

Non-local

35.19%

 

OWNER/EXECUTIVE

 

Rebcon, LLC

400 109th Street

Arlington, Texas 76011

 

Danny Krieg, President

 

MAP

 

Attached