Skip to main content
Dallas Logo
File #: 25-2521A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 8/6/2025 In control: Department of Facilities and Real Estate Management
On agenda: 9/10/2025 Final action:
Title: Authorize the ratification of an emergency change order to the work order for roof replacement at the Dallas Municipal Court located at 2014 Main Street with Brown and Root Industrial Services, LLC under the existing job order services contract, previously approved on March 8, 2023, by Resolution No. 23-0355, to include emergency protective measures in response to interior flooding caused by a severe rain event on July 9, 2025 - Not to exceed $9,996.00 - Financing: Capital Construction Fund
Indexes: 14
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Core

AGENDA DATE:                     September 10, 2025

COUNCIL DISTRICT(S):                     14

DEPARTMENT:                     Department of Facilities and Real Estate Management

EXECUTIVE:                     Donzell Gipson

______________________________________________________________________

SUBJECT

 

Title

Authorize the ratification of an emergency change order to the work order for roof replacement at the Dallas Municipal Court located at 2014 Main Street with Brown and Root Industrial Services, LLC under the existing job order services contract, previously approved on March 8, 2023, by Resolution No. 23-0355, to include emergency protective measures in response to interior flooding caused by a severe rain event on July 9, 2025 – Not to exceed $9,996.00 – Financing: Capital Construction Fund

 

Body

BACKGROUND

 

The Department of Facilities and Real Estate Management is currently undertaking a roof replacement project at Dallas Municipal Court building located at 2014 Main Street The work is being executed through a work order under the existing job order services contract, previously approved on March 8, 2023, by Resolution No. 23-0355, for construction services with Brown and Root Industrial Services, LLC.

 

On July 9, 2025, the Dallas area experienced a heavy rain event which caused interior flooding to the building. In response to this incident, emergency protective measures were implemented as part of the ongoing roof replacement project to prevent further water intrusion and minimize additional damage. The original work order was $460,657.00. During initial project planning, it was determined that the proposed insulation system needed modification to improve slopes for better roof drainage. A change order for $37,508.00 was issued, bringing the job order total to $498,165.00. On July 9, an emergency change order amounting to $9,996.00 was executed, raising the total project cost to $508,161.00 exceeding the $500,000.00 threshold that requires the City Council approval.

 

The change order had to be executed immediately to mitigate further damage to the City property and minimize the impact on the operations of the Courts facility. The added scope included removing areas of existing roof that were damaged during the storm and installing temporary roofing to prevent water infiltration during anticipated rain events.

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Project                                          July 2024

Complete Project                     September 2025

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On March 8, 2023, the City Council authorized a two-year contract, with three one-year renewal options with Brown and Root Industrial Services, LLC for job order services for minor construction, repairs, alterations, and improvements by Resolution No. 23-0355.

 

The City Council was briefed by memorandum regarding this matter on September 5, 2025.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Capital Construction

$9,996.00

$0.00

$0.00

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Brown and Root Industrial Services, LLC

Local

.3%

 

OWNER/EXECUTIVE

 

Brown and Root Industrial Services, LLC

 

Rick Farrag, Vice President

 

MAP

 

Attached