Legislation Details

File #: 26-1242A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 3/30/2026 In control: Department of Transportation and Public Works
On agenda: 5/13/2026 Final action:
Title: Authorize (1) an agreement with the Texas Department of Transportation for a U.S. Department of Transportation Federal Highway Administration Federal-Aid Project (CSJ 1068-04-181, Assistance Listing No. 20.205) in the amount of $401,527.50 to provide cost reimbursement for material and labor incurred by the City related to the construction of traffic signals at the following three intersections: Interstate Highway 30 and North (N) Cockrell Hill Road, Frankford Road and State Highway (SH) 190 (President George Bush Turnpike), and Coit Road and SH 190 (President George Bush Turnpike), and retiming of directly impacted signals in the area related to the construction; (2) the establishment of appropriations in the amount of $401,527.50 in the TxDOT HSIP 3-Signals Reimbursement at Highway (Hwy) 30 and N Cockrell Hill Fund; (3) the receipt and deposit of funds in the amount of $401,527.50 in the TxDOT HSIP 3-Signals Reimbursement at Hwy 30 and N Cockrell Hill Fund; and (4) execution of the a...
Indexes: 1, 12, 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     May 13, 2026

COUNCIL DISTRICT(S):                     1, 6, 12

DEPARTMENT:                     Department of Transportation and Public Works

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize (1) an agreement with the Texas Department of Transportation for a U.S. Department of Transportation Federal Highway Administration Federal-Aid Project (CSJ 1068-04-181, Assistance Listing No. 20.205) in the amount of $401,527.50 to provide cost reimbursement for material and labor incurred by the City related to the construction of traffic signals at the following three intersections: Interstate Highway 30 and North (N) Cockrell Hill Road, Frankford Road and State Highway (SH) 190 (President George Bush Turnpike), and Coit Road and SH 190 (President George Bush Turnpike), and retiming of directly impacted signals in the area related to the construction; (2) the establishment of appropriations in the amount of $401,527.50 in the TxDOT HSIP 3-Signals Reimbursement at Highway (Hwy) 30 and N Cockrell Hill Fund; (3) the receipt and deposit of funds in the amount of $401,527.50 in the TxDOT HSIP 3-Signals Reimbursement at Hwy 30 and N Cockrell Hill Fund; and (4) execution of the agreement and all terms, conditions, and documents required by the agreement - Total amount of $401,527.50 - Financing: TxDOT HSIP 3-Signals Reimbursement at Hwy 30 and N Cockrell Hill Fund

 

*In alignment with Vision Zero Plan.

 

Body

BACKGROUND

 

The Texas Department of Transportation (TxDOT) is constructing traffic signals and associated on-system intersection improvements at the following three intersections: Interstate Highway 30 and N Cockrell Hill Road (CSJ 1068-04-181) (Council Districts (CD) 1 and 6), Frankford Road and SH 190 (President George Bush Turnpike) (CSJ 2964-04-010) (CD 12), and Coit Road and SH 190 (President George Bush Turnpike) (CSJ 2964-05-034) (CD 12). The project will include the construction of new traffic signals; pedestrian and Americans with Disabilities Act - related improvements; signal retiming of directly impacted signals in the area of construction; and other related construction.

 

 

 

Project                                                                                                                                                                                             Council District

 

Interstate Highway 30 and N Cockrell Hill Road                                                                                                         1, 6

Frankford Road and SH 190 (President George Bush Turnpike)                                            12

Coit Road and SH 190 (President George Bush Turnpike)                                                                 12

 

To remain consistent with other equipment in the citywide system, the City of Dallas will provide a controller, cabinet, radar detection equipment, traffic signs, and battery backup equipment for the project. TxDOT will reimburse the City for material and labor costs.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          November 2026

Complete Construction                     April 2027

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

TxDOT HSIP 3-Signals Reimbursement at Hwy 30 and N Cockrell Hill Fund

$401,527.50

$0.00

$0.00

 

Council District                                                               Amount

 

            1                                          $  67,305.03

            6                                          $  67,305.02

          12                                          $266,917.45

 

     Total                                          $401,527.50

 

MAP

 

Attached