Authorize an increase in the construction services contract with Estrada Concrete Company, LLC to add funding to compensate the contractor for the additional emergency work needed to reconstruct the retaining wall located at 9000-9300 Block of South Audelia Road - Not to exceed $1,338,743.50, from $92,788,440.00 to $94,127,183.50 - Financing: Street and Alley Improvement Fund
Body
BACKGROUND
On January 8, 2025, the City Council authorized a construction services contract with Estrada Concrete Company, LLC for the 2025 Street Resurfacing Construction Contract, by Resolution No. 25-0127.
In mid-January 2025, the Department of Transportation and Public Works received an emergency inspection report regarding a 746-foot retaining wall at 9000-9300 Audelia Road, which was identified as being at high risk of collapse and posing a public safety threat to City residents. Following this, City staff engaged WJE, Inc. to conduct an engineering investigation and develop reconstruction plans for the retaining wall.
This action will authorize Change Order No.1 to the construction services contract with Estrada Concrete Company, LLC to add funding for the additional emergency work needed to reconstruct the retaining wall located at 9000-9300 Block of South Audelia Road.
ESTIMATED SCHEDULE OF PROJECT
Began Construction April 2025
Complete Construction October 2025
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On January 8, 2025, the City Council authorized a construction services contract with Estrada Concrete Company, LLC for the 2025 Street Resurfacing Construction Contract, by Resolution No. 25-0127.
FISCAL INFORMATION
Fund |
FY 2025 |
FY 2026 |
Future Years |
Street and Alley Improvement Fund |
$1,338,743.50 |
$0.00 |
$0.00 |
Construction Contract $92,788,440.00
Change Order No.1 (this action) $ 1,338,743.50
Total $94,127,183.50
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$1,338,743.50 |
Construction |
32.00% |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
65.00% |
100.00% |
$1,338,743.50 |
• This contract exceeds the M/WBE goal. |
• Estrada Concrete Company LLC - Local; Workforce - 76.60% Local |
OWNER/EXECUTIVE
Estrada Concrete Company, LLC
650 Skyline Drive
Hutchins, TX 75141
Chris Leach, Chief Operating Officer
MAP
Attached