Authorize a professional services contract with Multatech Engineering, Inc. for the engineering design of the 2020-2024 Unimproved Alley Program - Not to exceed $321,950.00 - Financing: General Fund
Body
BACKGROUND
The Fiscal Year 2019 approved budget included funds for an Unimproved Alley Maintenance Program. As a result of City Council requests and approval of this program, specifications were developed in-house for competitive bids for unimproved alley construction and maintenance. The project was publicly advertised, but no contractors submitted bids. The maintenance work was started with in-house forces and is currently ongoing. During the course of the maintenance field work, it was determined there was a need for civil engineering services to address drainage issues, identify sub-terrain utilities, or other field concerns; particularly on alleys in an extremely poor or failed condition.
The start of the two-step procurement process began on April 25, 2019 with the first advertisement for design services. Four firms submitted their qualifications for the 2020-2024 Unimproved Alley Maintenance Program. All firms were deemed qualified, and a Request for Proposal was sent to each of the firms. As a result of the two-step procurement process, Multatech Engineering Inc. was determined to be the most qualified proposer of four.
This action will authorize a professional services contract with Multatech Engineering, Inc. for the engineering design of the 2020-2024 Unimproved Alley Program.
ESTIMATED SCHEDULE OF PROJECT
Begin Design November 2019
Complete Design November 2020
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
General Fund - $321,950.00
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Category |
M/WBE Goal |
M/WBE % |
M/WBE $ |
$321,950.00 |
Architectural & Engineering |
25.66% |
100.00% |
$321,950.00 |
• This contract exceeds the M/WBE goal. |