PILLAR: Sustainable
AGENDA DATE: February 11, 2026
COUNCIL DISTRICT(S): 9
DEPARTMENT: Dallas Water Utilities Department
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with Archer Western Construction, LLC for additional work associated with major maintenance and rehabilitation improvements at Dallas Water Utilities Department’s raw water system facilities located at Lake Ray Hubbard - Not to exceed $899,220.00, from $33,075,920.00 to $33,975,140.00 - Financing: Water Capital Improvement G Fund
*In alignment with Water and Wastewater Capital Improvement Program.
Body
BACKGROUND
The Dallas Water Utilities Department (DWU) identified and evaluated 10 raw water facilities based on their age and condition, impact to the system, reliability, cost to operate, and frequency of repairs. The most critical raw water facilities were found to include the lake intake, Forney Pump Station, and Forney Dam at Lake Ray Hubbard. Lake Ray Hubbard is the only DWU reservoir owned and operated by the City of Dallas. The reservoir and associated water supply infrastructure were constructed in the late 1960’s and early 1970’s and several critical components require rehabilitation and replacement.
On August 10, 2022, the City Council authorized a construction services contract with Archer Western Construction, LLC for major rehabilitation and replacement of infrastructure at Lake Ray Hubbard. Improvements include traveling screens, sluice gate replacement at the intake, pump and valve replacement, site civil and groundwater monitoring improvements, monorail and bridge crane system improvements, new stop logs and storage building, spillway concrete repairs, spillway gate repairs, heating, ventilation, and air conditioning upgrades, and electrical and control improvements for the Forney Dam. The existing facilities have reached the end of their useful life, have limited operability, and are difficult to access and repair.
On August 28, 2024, the City Council authorized Change Order No.1 to the construction services contract with Archer Western Construction, LLC for improvements at Lake Ray Hubbard. During construction, additional work not within the original contract was identified and determined to be necessary to complete the proposed improvements. The additional work included repair of the tainter gates and inspection of the low flow West slide gates, services for the crane rail design, replacement of one 60-inch butterfly valve, meter flow vault, replacement of two pressure relief/pressure sustaining surge control valves, and installation of new doors and hardware at the Forney Pump Station electrical building and bulkhead storage building.
This action will authorize Change Order No. 2 in the construction services contract with Archer Western Construction, LLC for additional work identified during construction resulting from unforeseen field conditions, DWU requested betterments, and constructability impacts. The additional work includes custom equipment fabrications, repair and epoxy coating of existing flow control gates, rehabilitation of the dam low flow slide gates, piezometer installations and paving, bridge crane pier replacement, and miscellaneous dam and pump station site improvements. Approval of this change order will allow for the successful completion of the project in summer 2026.
ESTIMATED SCHEDULE OF PROJECT
Began Construction October 2022
Complete Construction June 2026
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On August 10, 2022, the City Council authorized a construction services contract with Archer Western Construction, LLC for major maintenance and rehabilitation improvements at Dallas Water Utilities Department’s raw water system facilities located at Lake Ray Hubbard by Resolution No. 22-1131.
On August 28, 2024, the City Council authorized an increase in the construction services contract with Archer Western Construction, LLC for additional work associated with Dallas Water Utilities Department’s raw water system facilities located at Lake Ray Hubbard by Resolution No. 24-1212.
FISCAL INFORMATION
|
Fund |
FY 2026 |
FY 2027 |
Future Years |
|
Water Capital Improvement G Fund |
$899,220.00 |
$0.00 |
$0.00 |
Construction Contract $32,082,400.00
Change Order No. 1 $ 993,520.00
Change Order No. 2 (this action) $ 899,220.00
Total Project Cost $33,975,140.00
LOCAL PARTICIPATION
|
Prime |
Status |
Workforce % |
|
Archer Western Construction, LLC |
Local |
7.90% |
OWNER/EXECUTIVE
Archer Western Construction, LLC
1411 Greenway Drive
Irving, Texas 75038
Daniel P. Walsh, President