File #: 23-2138    Version: 1 Name:
Type: CONSENT AGENDA Status: Deleted
File created: 8/15/2023 In control: Park & Recreation Department
On agenda: 9/13/2023 Final action:
Title: Authorize an increase in the construction services contract with Joel Brown & Co. LLC, dba J.B. & Co. LLC for additional construction services at the Fair Park Centennial Building Improvements Project located at 1001 Washington Avenue - Not to exceed $268,570.95, from $4,776,516.61 to $5,045,087.56 - Financing: Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund)
Indexes: 7
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life, Arts & Culture

AGENDA DATE:                     September 13, 2023

COUNCIL DISTRICT(S):                     7

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

Title

Authorize an increase in the construction services contract with Joel Brown & Co. LLC, dba J.B. & Co. LLC for additional construction services at the Fair Park Centennial Building Improvements Project located at 1001 Washington Avenue - Not to exceed $268,570.95, from $4,776,516.61 to $5,045,087.56 - Financing: Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund)

 

Body

BACKGROUND

 

This action will authorize Change Order No. 2 to the construction services contract with Joel Brown & Co. LLC, dba J.B. & Co. LLC, for additional construction services at the Fair Park Centennial Building Improvements Project located at 1001 Washington Avenue. 

 

The original scope of work consisted of mechanical improvements, roof replacement and column repairs at the Centennial Building in Fair Park. The increased scope includes additional improvements to the roofing system and reimbursements to the contractor for schedule changes made by the owner.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                                                July 2021

Design Completed                                                               June 2022

Began Construction                                                               March 2023

Complete Construction                                          June 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On January 25, 2023, the City Council authorized a construction services contract with J.B. & Co. LLC, for the construction of the Fair Park Centennial Building Improvements Project located at 1001 Washington Avenue by Resolution No. 230191.

 

On September 7, 2023, the Park and Recreation Board will consider authorizing a professional services contract with SWA Group for 1) surveying and platting services for park in the Cedars Park, near the intersection of South St. Paul Street and Beaumont Street; and 2) site assessment and analysis of the Old City Park site located at 1515 South Harwood Street.

 

FISCAL INFORMATION

 

Fund

FY 2023

FY 2024

Future Years

Fair Park Improvements (C) Fund (2017 General Obligation Bond Fund)

$268,570.95

$0.00

$0.00

 

Original Construction Contract                                           $  4,697,000.00

Change Order No. 1                                                                $       79,516.61

Change Order No. 2 (this action)                                          $     268,570.95

 

Total                                                                                                                              $  5,045,087.56‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬‬

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$268,570.95

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

75.62%

82.86%

$203,092.74

This contract exceeds the M/WBE goal.

Joel Brown & Co. LLC, dba J.B. & Co. LLC - Local; Workforce - 20.00% Local

 

OWNER

 

Joel Brown & Co. LLC, dba J.B. & Co. LLC

 

Joel Brown, President/Chief Executive Officer

 