Title: Authorize a professional services contract with DUNAWAY ASSOCIATES, LLC to provide engineering services for the evaluation and design of erosion control improvements at three locations (list attached to the Agenda Information Sheet) - Not to exceed $288,135.00 - Financing: Flood Protection and Storm Drainage (C) Fund (2024 General Obligation Bond Fund)
Indexes: 10, 12
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     August 27, 2025

COUNCIL DISTRICT(S):                     10, 12

DEPARTMENT:                     Dallas Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize a professional services contract with DUNAWAY ASSOCIATES, LLC to provide engineering services for the evaluation and design of erosion control improvements at three locations (list attached to the Agenda Information Sheet) - Not to exceed $288,135.00 - Financing: Flood Protection and Storm Drainage (C) Fund (2024 General Obligation Bond Fund)

 

Body

BACKGROUND

 

The City of Dallas has identified various properties experiencing severe erosion which have been included in the 2024 Bond Program. Engineering services are needed to evaluate options and develop construction documents to stabilize eroded stream banks utilizing gabion walls or other approved erosion control measures. The improvements will stabilize the existing stream banks while staying within the existing property boundary and floodway or erosion control easements.

 

This action will authorize a professional services contract with DUNAWAY ASSOCIATES, LLC for the engineering evaluation and design of erosion control improvements at three locations. Erosion control improvements will be evaluated and designed for Audelia Road 11655, Fortson Avenue 18503, and Nutwood Circle 6402. The services provided for this contract include project management, topographic and boundary surveys, easement document preparation, environmental permitting, subsurface utility exploration, geotechnical investigations, structural analysis, hydraulic analysis, and development of conceptual and final construction plans and special specifications.

 

The consulting firm for this project was selected following a qualifications-based selection process in accordance with the City of Dallas Administrative Directive 4-05 procurement guidelines.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Services                                          October 2025

Complete Services                                          October 2029

 

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Flood Protection and Storm Drainage (C) (2024 General Obligation Bond Fund)

$288,135.00

$0.00

$0.00

 

Council District                                             Amount

 

                     10                                                               $169,531.00

                     12                                                               $118,604.00

 

        Total                                                               $288,135.00

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

DUNAWAY ASSOCIATES, LLC

Local

18.46%

 

OWNER/EXECUTIVE

 

DUNAWAY ASSOCIATES, LLC

 

Chris H. Wilde, Chief Executive Officer

 

MAPS

 

Attached