SUBJECT
Title
Authorize Supplemental Agreement No. 6 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of a Bridge Management Program in support of the Infrastructure Management Plan, provide design and construction services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges - Not to exceed $500,000.00, from $792,921.00 to $1,292,921.00 - Financing: Street and Alley Improvement Fund
Body
BACKGROUND
The original professional services agreement with Wiss, Janney, Elstner Associates, Inc. began the development of a Bridge Management Program in support of the Infrastructure Management Plan (IMP) and to provide design and construction services on minor bridge repair projects. This contract was also amended through Council Resolutions and Administrative Actions to address design and construction phase services for three emergency bridge repairs that were identified through the Texas Department of Transportation (TxDOT) Bridge inspection program.
The original Bridge Management Plan identified 240 bridges needing additional inspections having a TxDOT Critical Rating of 6 or less. Due to budgetary constraints, 67 bridges were inspected in the first year with plans to address the remaining bridges in future years. Moving forward, the program will inspect an additional 60 to 70 bridges a year until all bridges have been evaluated. This is the third year of the program.
This action will authorize Supplemental Agreement No. 6 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of the Bridge Management Program in support of the IMP, provide design and construction services on minor bridge repair projects, and provide inspection and monitoring on multiple bridges.
Supplemental Agreement No. 6 will continue with the ongoing monitoring and development of the Bridge Maintenance program as well as ability to respond, inspect and report on bridge issues as they arise throughout the year.
Wiss, Janney, Elstner Associates, Inc. is a registered vendor with the City and has an office located in Irving, Texas.
ESTIMATED SCHEDULE OF PROJECT
Began Design September 2020
Complete Design December 2025
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On, September 23, 2020, City Council authorized the professional services contract with Wiss, Janney, Elstner Associates, Inc. by Resolution No. 20-1406.
On June 9, 2021, City Council authorized Supplemental Agreement No. 2 to the professional services contract with Wiss, Janney, Elstner Associates, Inc. for emergency design services for the Fitzhugh Bridge south of Fair Park by Resolution No. 21-0989.
On January 12, 2022, City Council authorized Supplemental Agreement No. 4 to the engineering services contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of the Bridge Management Program in support of the Infrastructure Management Plan, provide design and construction services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges by Resolution No. 22-0138.
FISCAL INFORMATION
Fund |
FY 2023 |
FY 2024 |
Future Years |
Street and Alley Improvement Fund |
$500,000.00 |
$0.00 |
$0.00 |
Design Contract
Design (PBW) $ 226,611.00
Supplemental Agreement No. 1 $ 19,500.00
Supplemental Agreement No. 2 $ 45,000.00
Supplemental Agreement No. 3 $ 0.00
Supplemental Agreement No. 4 $ 501,810.00
Supplemental Agreement No. 5 $ 0.00
Supplemental Agreement No. 6 (this action) $ 500,000.00
Total $1,292,921.00
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$500,000.00 |
Architecture & Engineering |
25.66%* |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
26.20% |
26.20% |
$131,000.00 |
• *This item reflects previous Business Inclusion and Development Policy MWBE goal |
• This contract exceeds the M/WBE goal. |
• Supplemental Agreement No. 6 - 22.89% Overall MWBE participation |
• Wiss, Janney, Elstner Associates, Inc- Local; Workforce - 6.15% Local |