Legislation Details

File #: 24-2284    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/22/2024 In control: Water Utilities Department
On agenda: 9/25/2024 Final action:
Title: Authorize a construction services contract for the replacement and rehabilitation of water and wastewater mains for the Hickory Creek Phase 2A Project (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of four - Not to exceed $12,538,800.00 - Financing: Water Construction Fund ($61,700.00), 2022C Water Revenue Bonds TWDB LM221535 Fund ($4,785,780.00), Wastewater Capital Improvement G Fund ($2,990,642.67), and Wastewater Capital Improvement F Fund ($4,700,677.33)
Indexes: 6, 8
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 25, 2024

COUNCIL DISTRICT(S):                     6, 8

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the replacement and rehabilitation of water and wastewater mains for the Hickory Creek Phase 2A Project (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of four - Not to exceed $12,538,800.00 - Financing: Water Construction Fund ($61,700.00), 2022C Water Revenue Bonds TWDB LM221535 Fund ($4,785,780.00), Wastewater Capital Improvement G Fund ($2,990,642.67), and Wastewater Capital Improvement F Fund ($4,700,677.33)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with Douglas Dailey Construction, LLC for the replacement and rehabilitation of approximately 27,470 feet of water and wastewater mains. This includes the installation of approximately 430 feet of 6-inch; and 6,240 feet of 8-inch diameter water mains, and 450 feet of 6-inch; 7,010 feet of 8-inch; 1,470 feet of 10-inch; 3,880 feet of 12-inch; 2,970 feet of 16-inch; 950 feet of 18-inch; 110 feet of 20-inch; 310 feet of 21-inch; 3,280 feet of 24-inch; and 370 feet of 36-inch diameter wastewater mains.

 

The existing water and wastewater mains targeted for replacement or rehabilitation were built between 1920 and 1964. The existing water and wastewater mains are being replaced or rehabilitated due to poor condition or the need for additional capacity. Mains planned for replacement will be upsized to meet future demands. Installation of the proposed segments will improve the capacity of the water and wastewater systems, reduce inflow and infiltration and Sanitary Sewer Overflows, reduce maintenance costs, and minimize service interruptions.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction          December 2024

Complete Construction    December 2026

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Water Construction Fund

$       61,700.00

$0.00

$0.00

Water 2022C Water Revenue Bonds TWDB LM221535 Fund

$  4,785,780.00

$0.00

$0.00

Wastewater Capital Improvement G Fund

$  2,990,642.67

$0.00

$0.00

Wastewater Capital Improvement F Fund

$  4,700,677.33

$0.00

$0.00

Total

$12,538,800.00

$0.00

$0.00

 

Council District                                          Amount

 

                     6                                                               $  1,300,000.00

                     8                                                               $11,238,800.00

 

                     Total                                                               $12,538,800.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$12,538,800.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

34.00%

34.00%

$4,263,192.00

• This contract exceeds the M/WBE goal.

• Douglas Dailey Construction, LLC - Local; Workforce - 22.86% Local

 

PROCUREMENT INFORMATION

 

The following four bids with quotes were received and opened on June 28, 2024:

 

*Denotes successful bidder

 

 

 

 

Bidders                                                                                                                                                     Bid Amount

 

*Douglas Dailey Construction, LLC                                                               $12,538,800.00

 2005 Bluff Springs Road

 Ferris, Texas 75125

John Burns Construction Company of Texas, LLC.                     $13,544,201.00

SYB Construction Co., Inc.                                                                                                         $13,801,132.50

Western Municipal Construction of Texas, LLC.                                          $14,460,755.00

 

OWNER

 

Douglas Dailey Construction, LLC

 

Douglas Dailey, Owner

 

MAPS

 