Title: Authorize Supplemental Agreement No. 7 to the professional services contract with Bartlett & West, Inc. to provide additional engineering design services for the Central Business District Fair Park Link from Hall Street to lnterstate Highway 30 - Not to exceed $88,980.00, from $886,191.32 to $975,171.32 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     January 24, 2024

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize Supplemental Agreement No. 7 to the professional services contract with Bartlett & West, Inc. to provide additional engineering design services for the Central Business District Fair Park Link from Hall Street to lnterstate Highway 30 - Not to exceed $88,980.00, from $886,191.32 to $975,171.32 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

 

Body

BACKGROUND

 

On January 23, 2008, the City Council authorized a professional services contract with Civil Associates, Inc. for the design of thoroughfare projects on the Central Business District (CBD) Fair Park Link from Hall Street to Interstate Highway 30 (IH 30), by Resolution No. 08-0324.

 

The original project scope includeds design of 1,425 linear feet, four 11-feet wide lanes divided with 15-feet wide median; 10-inch-thick reinforced concrete pavement; storm drainage; 6-feet wide sidewalks; 5-feet wide bike lanes; water and wastewater main improvements; streetscape improvements including landscaping and irrigation; Elm Street intersection improvement at the Dallas Area Rapid Transit (DART) rail; modification of the existing DART crossing gate arms and flashers at the Elm Street/Exposition Avenue intersection; and traffic signal and Light Emitting Diode pedestrian lighting.

 

On January 1, 2023, Civil Associates, Inc. merged with and into Bartlett & West, Inc. Also, Bartlett & West, Inc. assumed all terms and conditions of contractual agreements with Civil Associates, Inc.

 

On August 9, 2023, Administrative Action 23-6062 authorized a consent to assignment and assumption of services Civil Associates, Inc. to Bartlett & West, Inc. for the professional services contract for CBD Fair Park Link from Hall Street to IH 30.

 

During construction of the CBD Fair Park Link Project, a request was received from DART to complete a Preliminary Hazard Assessment (PHA) for the Elm Street at-grade railroad crossing before modifications can be made to this crossing.

 

Also, DART requested for a Systems Operation Basis of Design report to explain how the design for the at-grade crossing modification will operate and integrate into other supporting system elements, such as the traffic signal interfaces, to ensure safety of the public and to mitigate any hazards arising from the construction of the CBD Fair Park Link Project.

 

The report recommended to revise the Elm Street at-grade crossing design to accommodate the additional gates identified in the PHA and Basis of Design Report. Additionally, it is necessary to develop plans for the conversion of Elm Street from a one-way to a two-way traffic configuration for future use.

 

This action will authorize Supplemental Agreement No. 7 to the professional services contract with Bartlett & West, Inc. to provide additional engineering design services for CBD Fair Park Link from Hall Street to IH 30.

 

Bartlett & West, Inc. is a Kansas Dallas-based corporation operating within the corporate city limits of Dallas, Texas.

 

If this action is delayed or deferred, the construction schedule could be delayed. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                          January 2008

Complete Design                                          December 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On May 8, 2019, the City Council authorized Supplemental Agreement No. 5, to the professional services contract with Civil Associates, Inc. for additional engineering design of street lighting, plan revisions to incorporate recent adjacent private development, and necessary design modifications associated with the right-of-way acquisition needed for the Central Business District Fair Park Link from Hall Street to IH 30, by Resolution No. 19-0686.

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

$88,980.00

$0.00

$0.00

 

Engineering Services Contract                     $336,422.22

Supplemental Agreement No. 1                     $149,361.70

Supplemental Agreement No. 2                     29,693.20

Supplemental Agreement No. 3                     18,022.15

Supplemental Agreement No. 4                     85,884.00

Supplemental Agreement No. 5                     $251,110.00

Supplemental Agreement No. 6                     15,698.05

Supplemental Agreement No. 7 (this action)                     $  88,980.00

 

Total                     $975,171.32

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$88,980.00

Construction

25.66%*

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

0.00%

0.00%

$0.00

This contract does not meet the M/WBE.

This item reflects previous Business Inclusion Development Policy MWBE goal.

Barlette & West, Inc. - Local; Workforce - 18.00% Local

 

OWNER

 

Bartlett & West, Inc.

9330 Lyndon B. Johnson Freeway, Suite 1150

Dallas, Texas 75243

 

Naser Abusaad, P.E., AICP, Sr. Vice President

 

MAP

 

Attached