Title
Authorize (1) an agreement with the Texas Department of Transportation (TxDOT) for a U.S. Department of Transportation Federal Highway Administration (FHWA) federal-aid project (Agreement No. CSJ 0581-01-183, Assistance Listing No. 20.205), in the amount of $699,491.80 to provide cost reimbursement for material and labor incurred by the City related to the construction of traffic signals at the following intersections: East (E.) Ledbetter Drive and Corrigan Drive; South (S.) Great Trinity Forest Way and Haas Drive; S. Great Trinity Forest Way and Longacre Lane; S. Great Trinity Forest Way and S. Murdeaux Lane; S. Great Trinity Forest Way and Stoneport Drive; Horizon Drive and E. Ledbetter Drive; and Mystic Trail and E. Ledbetter Drive, and retiming of directly impacted signals in the area related to the construction; (2) the establishment of appropriations in the amount of $699,491.80 in the TxDOT Traffic Signal Reimbursement FHWA Seven Locations Great Trinity Forest Way Fund; (3) the receipt and deposit of funds in the amount of $699,491.80 in the TxDOT Traffic Signal Reimbursement FHWA Seven Locations Great Trinity Forest Way Fund; and (4) execution of the agreement and all terms, conditions, and documents required by the agreement - Total amount of $699,491.80 - Financing: TxDOT Traffic Signal Reimbursement FHWA Seven Locations Great Trinity Forest Way Fund
*In alignment with Capital Improvement Program. Vision Zero Plan.
Body
BACKGROUND
TxDOT is constructing traffic signals and associated on-system intersection improvements at the following intersections: E. Ledbetter Drive and Corrigan Drive; S. Great Trinity Forest Way and Haas Drive; S. Great Trinity Forest Way and Longacre Lane; S. Great Trinity Forest Way and S. Murdeaux Lane; S. Great Trinity Forest Way and Stoneport Drive; Horizon Drive and E. Ledbetter Drive; and Mystic Trail and E. Ledbetter Drive (Agreement No. CSJ 0581-01-183). The project will include the construction of new traffic signals; pedestrian and Americans with Disabilities Act related improvements; signal retiming of directly impacted signals in the area of construction; and other related construction.
Project Council District
E. Ledbetter Drive and Corrigan Drive 4, 8
S. Great Trinity Forest Way and Haas Drive 4, 8
S. Great Trinity Forest Way and Longacre Lane 8
S. Great Trinity Forest Way and S Murdeaux Lane 5, 8
S. Great Trinity Forest Way and Stoneport Drive 8
Horizon Drive and E. Ledbetter Drive 4, 8
Mystic Trail and E. Ledbetter Drive 3, 4
To remain consistent with other equipment in the citywide system, the City of Dallas will provide a controller, cabinet, radar detection equipment, traffic signs, and battery backup equipment for the project. TxDOT will reimburse the City for material and labor costs.
ESTIMATED SCHEDULE OF PROJECT
Began Construction August 2025
Complete Construction March 2026
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
|
Fund |
FY 2026 |
FY 2027 |
Future Years |
|
TxDOT Traffic Signal Reimbursement FHWA Seven Locations Great Trinity Forest Way Fund |
$699,491.80 |
$0.00 |
$0.00 |
Council District Amount
3 $ 56,144.90
4 $202,945.40
5 $ 25,153.98
8 $415,247.52
Total $699,491.80