File #: 24-2677    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/20/2024 In control: Water Utilities Department
On agenda: 9/25/2024 Final action:
Title: Authorize (1) acquisition from Jerry Dale Armstrong, Jr., of an industrially improved tract of land containing approximately 5.383 acres located on Botham Jean Boulevard near its intersection with South Central Expressway for the Dallas Floodway Extension Project; and (2) an increase in appropriations in an amount not to exceed $1,550,000.00 in the Trinity River Corridor Project Fund - Not to exceed $1,550,000.00 ($1,540,000.00, plus closing costs and title expenses not to exceed $10,000.00) - Financing: Trinity River Corridor Project Fund (subject to appropriations)
Indexes: 7
Attachments: 1. Map, 2. Resolution, 3. Exhibit A
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 25, 2024

COUNCIL DISTRICT(S):                     7

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize (1) acquisition from Jerry Dale Armstrong, Jr., of an industrially improved tract of land containing approximately 5.383 acres located on Botham Jean Boulevard near its intersection with South Central Expressway for the Dallas Floodway Extension Project; and (2) an increase in appropriations in an amount not to exceed $1,550,000.00 in the Trinity River Corridor Project Fund - Not to exceed $1,550,000.00 ($1,540,000.00, plus closing costs and title expenses not to exceed $10,000.00) - Financing: Trinity River Corridor Project Fund (subject to appropriations)

 

Body

BACKGROUND

 

The City of Dallas is the owner and operator of the Dallas Levee System extending from the Elm and West Forks of the Trinity River through the main stem and terminating at Interstate Highway 20. This system is regulated by the U.S. Army Corps of Engineers (USACE). In addition to regulating the Dallas Levee System, the USACE and City have been cost participating in two separate federal projects to improve the public safety of the residents and businesses that are served by this system. The City is required to own, in fee simple, all parcels related to the Dallas Levee System.

 

In July 2018, the Dallas Levee System flood risk management projects included in the Modified Dallas Floodway Project (DF) and the Dallas Floodway Extension (DFE) were authorized for funding under the Supplemental Appropriation in the Bipartisan Budget Act of 2018- Public Law 115-123 (PL-115-123). This information has been presented to the City Council and provided in memorandum to the City Council at major milestones since the notification by the USACE. All work associated with the design and construction of these improvements is being performed by USACE with the City serving as a technical advisor and client. An overview of the projects, federal funding and associated local requirements included in PL-115-123 are, as follows:

 

- DFE: Up to $135.25M for Lamar Levee and Cadillac Heights Levee

 

City is obligated to expend funds to complete necessary real estate activities such as acquisition, relocation and environmental remediation and public utility relocation; acquisition funds are potentially eligible for reimbursement in the future.

 

- DF: $261.9M for approved flood risk management such as levee raises and flattening, removal of ATSF Bridge, Trinity Portland Pump Station, Charlie Pump Station, Delta Pump Station Rehabilitation, Hampton Pump Station and Nobles Sump Improvements

City is obligated to expend funds on 35 percent of the design and construction and environmental remediation and public utility relocation; the real estate funds are credits against the cost share for the project.

 

This item authorizes the acquisition of an industrially improved tract of land containing approximately 5.383 acres, from Jerry Dale Armstrong, Jr.  The property is located on Botham Jean Boulevard near its intersection with South Central Expressway and will be used for the Dallas Floodway Extension Project. The consideration is based on an independent appraisal. Future relocation assistance may be necessary for this acquisition.

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 12, 2015, the City Council authorized reprograming the remaining bond funds from the 1998 Bond Proposition 11 from the Trinity Lakes and Trinity Parkway to other flood control improvement consistent with the bond proposition approved by the voters, by Resolution No. 15-1486.

 

The Mobility Solutions, Infrastructure and Sustainability Committee was briefed by memorandum regarding the projects and requirements related to the US Army Corps of Engineers Supplemental Bi- Partisan Budget Act of 2018 (PL 115-123) on April 19, 2019. <https://dallascityhall.com/government/Council%20Meeting%20Documents/msis_5__supplemental-appropriation-in-the-bipartisan-budget-act-of-2018-update-on-flood-risk-management-projects_memo_042219.pdf>

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Trinity River Corridor Project Fund

$1,550,000.00

$0.00

$0.00

 

OWNER

 

Jerry Dale Armstrong, Jr.

 

MAP

 

Attached