STRATEGIC PRIORITY: Sustainable
AGENDA DATE: June 25, 2025
COUNCIL DISTRICT(S): 1, 2, 3, 4, 7, 8, 14
DEPARTMENT: Dallas Water Utilities Department
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT
Title
Authorize a construction services contract for water and wastewater main replacements at 18 locations - SYB Construction Co., Inc., lowest responsible bidder of six - Not to exceed $14,656,533.31 - Financing: 2023C Water Revenue Bonds TWDB LM231535 Fund ($6,926,511.51) and Wastewater Capital Improvement F Fund ($7,730,021.80)
Body
BACKGROUND
This action will authorize a construction services contract with SYB Construction Co., Inc. for the installation of approximately 22,401 feet of water and wastewater mains. This includes installation of approximately 256 feet of 6-inch, 10,945 feet of 8-inch, 165 feet of 12-inch, 45 feet of 16-inch, and 630 feet of 24-inch diameter water mains and the installation of approximately 7,770 feet of 8-inch, 140 feet of 12-inch, 690 feet of 16-inch, 1080 feet of 18-inch, and 680 feet of 24-inch diameter wastewater mains.
The existing water and wastewater mains were built between 1910 and 1967. These mains are contributing to an increase in maintenance costs, as well as service interruptions. The installation of the proposed segments will improve the capacity of the water and wastewater systems and reduce maintenance costs.
The following chart illustrates SYB Construction Co., Inc.’s contractual activities with the City of Dallas for the past three years:
TRN DWU PKR PBW
Projects Completed 0 0 0 0
Active Projects 0 3 0 0
Change Orders 0 1 0 0
Projects Requiring Liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0
ESTIMATED SCHEDULE OF PROJECT
Begin Construction August 2025
Complete Construction September 2027
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Fund |
FY 2025 |
FY 2026 |
Future Years |
2023C Water Revenue Bonds TWDB LM231535 Fund |
$6,926,511.51 |
$0.00 |
$0.00 |
Wastewater Capital Improvement F Fund |
$7,730,021.80 |
$0.00 |
$0.00 |
Total |
$14,656,533.31 |
$0.00 |
$0.00 |
Council District Amount
1 $6,453,880.08
2 $2,928,178.27
3 $ 256,528.44
4 $2,496,459.68
7 $ 794,612.48
8 $ 594,395.16
14 $1,132,479.20
Total $14,656,533.31
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$14,656,533.31 |
Construction |
32.00% |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
32.68% |
32.68% |
$4,789,354.52 |
• This contract exceeds the M/WBE goal. |
• SYB Construction Co., Inc. - Non-local; Workforce - 30.71% Local |
PROCUREMENT INFORMATION
The following six bids with quotes were received on April 4, 2025:
*Denotes successful bidder
Bidders Bid Amount
*SYB Construction Co., Inc. $14,656,533.31
1017 S FM 157
Venus, TX 76084
Douglas Daily Construction, LLC $15,465,621.00
Camino Construction, L.P. $16,988,273.00
Western Municipal Construction of Texas, LLC $18,290,370.00
Omega Contracting, LLC $19,608,195.70
John Burns Construction Company of Texas, LLC $20,529,136.00
OWNER/EXECUTIVE
SYB Construction Co., Inc.
Brian Wood, Vice President
MAPS
Attached