Skip to main content
Dallas Logo
File #: 24-627    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 2/13/2024 In control: Water Utilities Department
On agenda: 4/10/2024 Final action:
Title: Authorize an increase in the construction services contract with Douglas Dailey Construction, LLC for additional work associated with the installation of water services, large valve manholes, dewatering efforts for construction, and additional paving and surface restoration work - Not to exceed $750,410.00, from $13,921,735.00 to $14,672,145.00 - Financing: Water Capital Improvement F Funds ($558,035.00) and Wastewater Capital Improvement F Funds ($192,375.00)
Indexes: 1, 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     April 10, 2024

COUNCIL DISTRICT(S):                     1, 6

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Douglas Dailey Construction, LLC for additional work associated with the installation of water services, large valve manholes, dewatering efforts for construction, and additional paving and surface restoration work - Not to exceed $750,410.00, from $13,921,735.00 to $14,672,145.00 - Financing: Water Capital Improvement F Funds ($558,035.00) and Wastewater Capital Improvement F Funds ($192,375.00)

 

Body

BACKGROUND

 

On May 25, 2022, the City Council authorized a construction services contract for the replacement and rehabilitation of approximately 27,884 feet of water and wastewater mains at 13 locations by Resolution No. 22-0816. During construction at Luna Road from Northwest Highway (Loop 12) to Royal Lane, Dallas Water Utilities (DWU) encountered unforeseen site, soil, groundwater, and vegetation conditions requiring extensive dewatering efforts; determined the need for additional water service installations at locations where previously unidentified existing water meters were exposed during construction; and made design modifications to include large valve manholes for future access improvements. At another location on Jefferson Boulevard from Ravinia Drive northeast, it was also determined that additional concrete curb and gutter replacement and pavement extension was necessary. Available funding under the original contract will not be adequate to address the additional work.

 

This action will authorize Change Order No. 1 to the construction services contract with Douglas Dailey Construction, LLC for additional funding needed to complete the ongoing installation of the water and wastewater improvements at Luna Road and Jefferson Boulevard. The existing water and wastewater mains are identified to be aging and in need of repair and replacement due to poor condition, service interruptions and increased maintenance efforts. Some of these mains also need to be upsized to meet future demands. For these reasons, there is strong need to complete the additional work described above in a timely manner to improve the capacity of the water/wastewater system, reduce maintenance efforts/costs, and avoid service interruptions.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                                          June 2022

Complete Construction                     June 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On May 25, 2022, the City Council authorized a construction services contract for the installation and rehabilitation of water and wastewater mains and appurtenances at 13 locations by Resolution No. 22-0816.

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Water Capital Improvement F Funds

$558,035.00

$0.00

$0.00

Wastewater Capital Improvement F Funds

$192,375.00

$0.00

$0.00

Total

$750,410.00

$0.00

$0.00

 

Construction                     $13,921,735.00

Change Order No. 1 (this action)                     $     750,410.00

                     

Total                     $14,672,145.00

 

Council District                                                   Amount

                     

                     1                                                                     $261,500.00

                     6                                                                     $488,910.00

 

       Total                                                                     $750,410.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$750,410.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

34.00%

34.00%

$255,139.40

This contract exceeds the M/WBE goal.

Change Order No. 1 - 34.00% Overall Participation

Douglas Dailey Construction, LLC - Non-Local; Workforce - 22.85.00% Local

 

OWNER

 

Douglas Dailey Construction, LLC

 

Douglas Dailey, President

 

MAP

 

Attached