File #: 25-1834A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 5/16/2025 In control: Department of Transportation and Public Works
On agenda: 6/25/2025 Final action:
Title: Authorize payment to the Texas Department of Transportation for the Advance Funding Agreement (Agreement No. CSJ 0918-47-403, etc., Assistance Listing No. 20.205) for cost overruns related to the construction of six traffic signals and associated off-system intersection improvements at the following locations: Eastridge Drive at Skillman Street, Forest Lane at Josey Lane, Frankford Road at Vail Street, Cedar Springs Road at Manor Way, Greenville Avenue at Markville Drive, and Hillcrest Road at Royal Lane - Total amount of $652,299.00 - Financing: General Fund
Indexes: 10, 11, 12, 13, 2, 6, 9
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     June 25, 2025

COUNCIL DISTRICT(S):                     2, 6, 9, 10, 11, 12, 13

DEPARTMENT:                     Department of Transportation and Public Works

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize payment to the Texas Department of Transportation for the Advance Funding Agreement (Agreement No. CSJ 0918-47-403, etc., Assistance Listing No. 20.205) for cost overruns related to the construction of six traffic signals and associated off-system intersection improvements at the following locations: Eastridge Drive at Skillman Street, Forest Lane at Josey Lane, Frankford Road at Vail Street, Cedar Springs Road at Manor Way, Greenville Avenue at Markville Drive, and Hillcrest Road at Royal Lane - Total amount of $652,299.00 - Financing: General Fund

 

Body

BACKGROUND

 

The Texas Department of Transportation (TxDOT) administers the Federal Highway Safety Improvement Program, which provides grant funding to reconstruct traffic signals at high-accident intersections in the city of Dallas.

 

On August 28, 2024, the City Council authorized an Advance Funding Agreement (AFA) with TxDOT for the design, upgrade, and construction of six traffic signals and associated off-system intersection improvements at the following locations:

 

Off-System Intersections:

 

                     Cedar Springs Road at Manor Way (CSJ 0918-47-406), (CD2)

                     Eastridge Drive at Skillman Street (CSJ 0918-47-403), (CD9, CD13)

                     Forest Lane at Josey Lane (CSJ 0918-47-404), (CD6, CD13)

                     Frankford Road at Vail Street (CSJ 0918-47-405), (CD12)

                     Greenville Avenue at Markville Drive (CSJ 0918-47-408), (CD10)

                     Hillcrest Road at Royal Lane (CSJ 0918-47-411), (CD11, CD13)

 

The AFA included a required local match in the amount of $582,355.85 ($282,355.85 for direct state costs paid to TxDOT and an estimated cost burden of $300,000.00 for design).

 

 

All six traffic signal locations are on the Vision Zero High Injury Network, which identifies city streets that account for a disproportionate number of fatal and severe crashes. Reconstructing these traffic signals may improve safety and contribute to advancing the City’s Vision Zero goal of eliminating traffic fatalities and reducing severe injuries.

 

Due to sharp increases in material costs since the original construction estimates were prepared, primarily in traffic signal poles and concrete, the lowest bid for the six intersections exceeded estimates by $652,299.00.

 

This action will authorize payment to TxDOT for the cost overrun amount for the six intersections as agreed to in the AFA.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          July 2025

Complete Construction                     July 2027

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 28, 2024, the City Council authorized an AFA with TxDOT in the estimated amount of $3,707,223.51 for a U.S. Department of Transportation - Federal Highway Administration 2021 Highway Safety Improvement Program grant (Agreement No. CSJ 0918-47-403, etc., Assistance Listing No. 20.205) in the amount of $2,974,286.00 as Federal participation, $582,355.85 ($282,355.85 for direct state costs paid to TxDOT and an estimated $300,000.00 for design) as local participation, and $151,571.66 as State participation for indirect state costs to construct traffic signal improvements at the following six locations: Eastridge Drive at Skillman Street (CSJ 0918-47-403), Forest Lane at Josey Lane (CSJ 0918-47-404), Frankford Road at Vail Street (CSJ 0918-47-405), Cedar Springs Road at Manor Way (CSJ 0918-47-406), Greenville Avenue at Markville Drive (CSJ 0918-47-408), and Hillcrest Road at Royal Lane (CSJ 0918-47-411) by Resolution No. 24-1178.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

General Fund

$652,299.00

$0.00

$0.00

 

Council District                         Amount

 

          2                                          $  96,540.25

          6                                          $  58,054.61

          9                                          $  49,574.72

         10                                          $110,238.53

         11                                          $  82,189.69

         12                                          $120,675.31

         13                                          $135,025.89

 

        Total                                          $652,299.00

 

MAP

 

Attached