Dallas Logo
File #: 23-1853    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/10/2023 In control: Department of Public Works
On agenda: 9/27/2023 Final action:
Title: Authorize a construction services contract for the construction of Street Reconstruction Group 17-6007 (list attached to the Agenda Information Sheet) - Camino Construction, L.P., lowest responsible bidder of three - Not to exceed $2,973,594.50 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($1,994,154.50), Water Construction Fund ($356,710.00), and Wastewater Construction Fund ($622,730.00)
Indexes: 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 27, 2023

COUNCIL DISTRICT(S):                     6

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the construction of Street Reconstruction Group 17-6007 (list attached to the Agenda Information Sheet) - Camino Construction, L.P., lowest responsible bidder of three - Not to exceed $2,973,594.50 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($1,994,154.50), Water Construction Fund ($356,710.00), and Wastewater Construction Fund ($622,730.00)

 

Body

BACKGROUND

 

This action will authorize a construction services contract with Camino Construction, L.P., for the construction of two street reconstruction projects as Street Reconstruction Group 17-6007.

 

The project group scope will include replacing the existing deteriorating concrete streets with reinforced concrete pavement, curb, gutter, driveway approaches, sidewalks, storm drainage, water and wastewater improvements, and other miscellaneous items necessary to complete the project in accordance with the design plans and specifications.

 

Following are the locations and construction cost for each project:

 

Project                     Council District                         Amount

 

North Morocco Avenue from

Goodman Street to North Justin Avenue                                          6                                          $1,327,114.00

 

Shaw Street from Navaro Street

to Harston Street                                          6                                          $1,646,480.50

 

Camino Construction, L.P. is a Lewisville, Texas-based corporation and is a registered vendor with the City of Dallas.

 

The following chart illustrates Camino Construction, L.P.’s, contractual activities with the City of Dallas for the past three years.

 

                     PBW                     DWU                     PKR                     TRN

 

Active Projects                                          3                     1                                          0                     0

Projects Completed                     6                     0                     0                     0

Change Orders                     1                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

If this project group is not awarded for construction at this time, the roadways will continue to deteriorate causing additional pavement cracking and potholes to form, creating additional maintenance costs for the City and potential damages to vehicles utilizing the roadways. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          December 2023

Complete Construction                     January 2025

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2023

FY 2024

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

$1,994,154.50

$0.00

$0.00

Water Construction Fund

$   356,710.00

$0.00

$0.00

Wastewater Construction Fund

$   622,730.00

$0.00

$0.00

Total

$2,973,594.50

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

 

 

 

 

 

Contract Amount

Procurement Category

M/WBE Goal

$2,973,594.50

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

32.65%

70.93%

$2,109,256.50

This contract does not meet the M/WBE goal, but complies with good faith efforts.

Camino Construction, L.P. - Non-local; Workforce - 75.00% Local

 

PROCUREMENT INFORMATION

 

The following three bids were received and opened on June 23, 2023:

*Denotes successful bidder

Bidders                                                                                                         Bid Amount

*Camino Construction, L.P.                     $2,973,594.50

 1208 Metro Park Boulevard

 Lewisville, Texas, 75057

Estrada Concrete Company, LLC                                                                                    $3,012,889.25

Jeske Construction Company                                                                                    $3,208,360.00

 

OWNER

 

Camino Construction, L.P.

Rogelio Ayala, President

 

MAPS

 

Attached