Title: Authorize a professional services contract with UES Professional Solutions 44, LLC for the construction material testing services for pavement surface improvements for the construction of Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard - Not to exceed $120,934.00 - Financing: 2024B Certificates of Obligation Fund
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     December 11, 2024

COUNCIL DISTRICT(S):                     6

DEPARTMENT:                     Departmenf of Transportation and Public Works

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize a professional services contract with UES Professional Solutions 44, LLC for the construction material testing services for pavement surface improvements for the construction of Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard - Not to exceed $120,934.00 - Financing: 2024B Certificates of Obligation Fund

 

Body

BACKGROUND

 

The request for qualifications (CIZ-DWU-22 309E) was issued in July 2022 for the 2022 construction material testing services. The consulting firm, UES Professional Solutions 44, LLC was selected following a qualifications-based selection process in accordance with the City of Dallas procurement guidelines.

 

This action will authorize a professional services contract with UES Professional Solutions 44, LLC for the construction material testing services for pavement surface improvements for Cockrell Hill Road from La Reunion Parkway to Singleton Boulevard scope of work. These testing services are required to ensure that the material utilized during construction is in conformance with the quality required by the project specifications.

 

The following is the location and material testing services cost:

 

Project                                                                                                                 Council District                     Amount

 

Cockrell Hill Road from La Reunion                            6                      $120,934.00

Parkway to Singleton Boulevard PB17V136

 

 

 

 

 

 

The following chart illustrates UES Professional Solutions 44, LLC's contractual activities with the City of Dallas for the past three years:

 

 

 

                                                                                                                                                                        AVI      DWU      PKR     TPW

 

Projects completed                     0                     0                     2                     3

Active Projects                     0                     2                     1                     1

Change Orders                     0                     0                     0                     0

Projects Requiring Liquidated Damages                     0                     0                     0                     0

Projects Completed by Bonding Company                     0                     0                     0                     0

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                  June 2025

Complete Construction            March 2028

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

2024B Certificates of Obligation Fund

$120,934.00

$0.00

$0.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$120,934.00

Professional Services

38.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

38.00%

38.00%

$45,954.92

This contract meets the M/WBE goal.

UES Professional Solutions 44, LLC - Local; Workforce - 21.36% Local

 

 

 