File #: 25-2527A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 8/6/2025 In control: Department of Transportation and Public Works
On agenda: 9/10/2025 Final action:
Title: Authorize an Advance Funding Agreement with the Texas Department of Transportation (TxDOT) in the amount of $3,530,454.18 for a U.S. Department of Transportation Federal Highway Administration 2022 Highway Safety Improvement Program grant (Agreement No. CSJ 0091-06-062, etc., Assistance Listing No. 20.205) in the amount of $2,788,567.90 as federal participation for construction, $371,618.79 as state participation for construction, direct state cost, and indirect state cost, and $370,267.49 ($160,267.49 for direct state cost paid to TxDOT and an estimated $210,000.00 for design) plus any cost overruns as local participation to construct traffic signal improvements at six locations (list attached to Agenda Information Sheet) - Total amount of $160,267.49 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund)
Indexes: 10, 11, 12, 13, 2, 5, 6, 7, 9
Attachments: 1. List, 2. Map, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     September 10, 2025

COUNCIL DISTRICT(S):                     2, 5, 6, 7, 9, 10, 11, 12, 13

DEPARTMENT:                     Department of Transportation and Public Works

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize an Advance Funding Agreement with the Texas Department of Transportation (TxDOT) in the amount of $3,530,454.18 for a U.S. Department of Transportation Federal Highway Administration 2022 Highway Safety Improvement Program grant (Agreement No. CSJ 0091-06-062, etc., Assistance Listing No. 20.205) in the amount of $2,788,567.90 as federal participation for construction, $371,618.79 as state participation for construction, direct state cost, and indirect state cost, and $370,267.49 ($160,267.49 for direct state cost paid to TxDOT and an estimated $210,000.00 for design) plus any cost overruns as local participation to construct traffic signal improvements at six locations (list attached to Agenda Information Sheet) – Total amount of $160,267.49 – Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund)

 

Body

BACKGROUND

 

The City of Dallas was awarded a grant of $2.8 million from the 2022 Highway Safety Improvement Program administered by TxDOT to complete traffic signal improvements at 6 locations. Upgrades may include visor replacements on traffic signal heads; removal of existing traffic signals and replacing them with new traffic signals; pedestrian and Americans with Disabilities Act improvements; and other related construction.

 

The City is responsible for the design of the traffic signals with an estimated cost burden of $210,000.00 and is responsible for 100 percent of the direct state cost to be paid to TxDOT in the amount of $160,267.49. TxDOT is responsible for bidding the construction package, administering the federal funds for construction in an estimated amount of $2,788,567.90, and contributing construction and indirect state cost in an estimated amount of $371,618.79. The total estimated project cost is $3,530,454.18. Although it is not anticipated, the City may be responsible for cost associated with utilities, environmental assessment and mitigation, architectural and engineering services, and right-of-way and real property if TxDOT determines that the specific work is necessary for successful completion of the project.

 

 

On-System Intersections:

 

                     Interstate Highway (IH) 635 from TI Boulevard to IH-35E (CSJ 2374-01-196) (visor replacements only)

                     Preston Road (State Highway 289) from Northwest Highway (State Loop 12) to President George Bush Turnpike (State Highway 190) (CSJ 0091-06-062) (visor replacements only)

                     Northwest Highway (State Loop 12) at Shady Brook Lane (CSJ 0353-05-133)

 

Off-System Intersections:

 

                     Bruton Road at Northeast Hillburn Drive (0918-47-444)

                     Lake June Road at St. Augustine Road (0918-47-446)

                     Oates Drive at Shiloh Road (0918-47-450)

 

This action will authorize local participation in the amount of $160,267.49 to be disbursed to TxDOT.

 

Any change orders or overruns for the off-system intersections are the responsibility of the City of Dallas.

 

Construction of the traffic signals is scheduled to begin in FY 2026.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                                           September 2024

Complete Design                                           September 2025

Begin Construction                                          April 2026

Complete Construction                     April 2028

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 11, 2024, the City Council authorized a professional engineering services contract with WSB LLC, for traffic signal design services for the four intersections in Group 12 as follows: Northwest Highway and Shady Brook Lane, Bruton Road at Hillburn Drive, Lake June Road at St. Augustine Road, Oates Drive and Shiloh Road; and other related tasks, by Resolution No. 24-1284.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Street and Transportation (A) Fund (2024 General Obligation Bond Fund)

$160,267.49

$0.00

$0.00

 

 

 

 

 

 

 

Council District                        Amount

 

          2                                          $  17,807.50

          5                                          $  17,807.50

          6                                          $  17,807.50

          7                                          $  17,807.50

          9                                          $  17,807.50

          10                                          $  17,807.50

          11                                          $  17,807.50

          12                                          $  17,807.50

          13                                          $  17,807.49

 

        Total                                          $160,267.49

 

MAP

 

Attached