STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: February 26, 2025
COUNCIL DISTRICT(S): 2
DEPARTMENT: Department of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with Rebcon, LLC for the additional wastewater improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue - Not to exceed $286,347.68, from $30,061,949.00 to $30,348,296.68 - Financing: Wastewater Capital Improvement G Fund
Body
BACKGROUND
On September 27, 2023, the City Council authorized the construction services contract with Rebcon, LLC for the construction of Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 23-1324.
During construction, it was discovered that the existing clay wastewater line in Walton Street was too fragile to survive the proposed encasement work. Consequently, it is necessary to add the additional wastewater improvements needed to replace the fragile wastewater line in Walton Street to the contract.
This action will authorize Change Order No. 2 to the construction services contract with Rebcon, LLC for the additional wastewater improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue.
ESTIMATED SCHEDULE OF PROJECT
Began Construction March 2024
Complete Construction December 2026
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On September 27, 2023, the City Council authorized the construction services contract with Rebcon, LLC for the construction of Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 23-1324.
FISCAL INFORMATION
Fund |
FY 2025 |
FY 2026 |
Future Years |
Wastewater Capital Improvement G Fund |
$286,347.68 |
$0.00 |
$0.00 |
Construction Contract $29,968,199.00
Change Order No. 1 $ 93,750.00
Change Order No. 2 (this action) $ 286,347.68
Total $30,348,296.68
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$286,347.68 |
Construction |
32.00% |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
0.00% |
0.00% |
$0.00 |
• This contract does not meet the M/WBE goal, but complies with good faith efforts. |
• Rebcon, LLC - Non-local; Workforce - 30.00% Local |