Dallas Logo
File #: 24-2281    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 7/22/2024 In control: Water Utilities Department
On agenda: 9/11/2024 Final action:
Title: Authorize an increase in the construction services contract with Archer Western Construction, LLC, for additional work associated with improvements to the ozone generation facilities at the Bachman, East Side, and Elm Fork Water Treatment Plants - Not to exceed $1,073,195.26, from $36,420,755.00 to $37,493,950.26 - Financing: Water Construction Fund
Indexes: 200, 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     September 11, 2024

COUNCIL DISTRICT(S):                     6, Outside City Limits

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Archer Western Construction, LLC, for additional work associated with improvements to the ozone generation facilities at the Bachman, East Side, and Elm Fork Water Treatment Plants - Not to exceed $1,073,195.26, from $36,420,755.00 to $37,493,950.26 - Financing: Water Construction Fund

 

Body

BACKGROUND

 

Dallas Water Utilities (DWU) operates three potable water treatment plants (Bachman, East Side, and Elm Fork) and provides water to approximately 2.6 million customers in the City of Dallas and neighboring communities. The combined treatment capacity of these facilities is approximately 900 million gallons per day. Ozone is the primary water treatment disinfectant at all three plants and allows DWU to comply with federal regulations governing disinfection by-products and improves the finished water quality by destroying taste and odor causing compounds.  The first ozone system was installed at Elm Fork Water Treatment Plant in the early 1990’s and ozone facilities were added to the East Side and Bachman Water Treatment Plants in 2002 and 2006 respectively.

 

An evaluation of critical performance limiting factors was completed at each plant, which identified the need to replace the ozone generating equipment. On September 23, 2020, the City Council authorized a construction services contract with Archer Western Construction, LLC for the replacement of the ozone generating equipment and appurtenances at the water treatment plants. The contract includes the purchase and installation of three new generators and associated equipment at Bachman, four new generators and associated equipment at East Side, and four new generators at Elm Fork.  The project also includes new liquid oxygen tanks with the capacity to meet the entire production needs at East Side, the relocation of refurbished tanks to increase storage capacity and the installation of a second transformer and power supply system at Elm Fork and needed modifications to the ozone delivery system at Bachman.

 

 

 

This action will authorize Change Order No. 1 to the construction services contract to include changes and betterments required for the completed facilities to function as intended. It also includes repairs, modifications and additions to address deficiencies not identified during design due to site access restrictions. The additional work covers various components including valves, piping, pump, equipment, electrical, instrumentation, slab repairs, building and civil modifications. The ozone system is a critical treatment component at all three plants and the current equipment requires significant time and materials to maintain. The additional work will ensure the ozone facility improvements address the reliability and efficiency of these systems to meet demands now and in the future, while reducing operation and maintenance costs.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                November 2020

Complete Construction           December 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 23, 2020, the City Council authorized a construction services contract for improvements to the ozone generation facilities at the Bachman, East Side, and Elm Fork Water Treatment Plants - Archer Western Construction, LLC, by Resolution No. 20-1467.

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Water Construction Fund

$1,073,195.26

$0.00

$0.00

 

Construction                                                   $36,420,755.00

Change Order No. 1 (this action)                   $  1,073,195.26

 

Total Project Cost                                           $37,493,950.26

 

Council District                                 Amount

 

            6                                              $181,840.00

Outside City Limits                              $891,355.26

 

         Total                                           $1,073,195.26

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

 

 

 

Contract Amount

Procurement Category

M/WBE Goal

$1,073,195.26

Construction

25.00%*

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

6.54%

6.54%

$70,227.38

This contract does not meet the M/WBE goal, but complies with good faith efforts.

Change Order No 1 - 8.27% MWBE Overall Participation

Archer Western Construction LLC - Local; Workforce - 8.00% Local

 

OWNER/EXECUTIVE

 

Archer Western Construction, LLC

 

Daniel P. Walsh, President

 

MAPS

 

Attached