Skip to main content
Dallas Logo
File #: 26-134A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 12/8/2025 In control: Dallas Water Utilities Department
On agenda: 1/28/2026 Final action:
Title: Authorize an increase in the construction services contract with Camino Construction, L.P., for additional work associated with water and wastewater main improvements at 17 locations (list attached to the Agenda Information Sheet) - Not to exceed $880,000.00, from $21,319,817.00 to $22,199,817.00 - Financing: Water Construction Fund ($415,000.00) and Wastewater Construction Fund ($465,000.00) *In alignment with Water and Wastewater Capital Improvement Program.
Indexes: 14, 2, 3, 6, 7, 8
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     January 28, 2026

COUNCIL DISTRICT(S):                     2, 3, 6, 7, 8, 14

DEPARTMENT:                     Dallas Water Utilities Department

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Camino Construction, L.P., for additional work associated with water and wastewater main improvements at 17 locations (list attached to the Agenda Information Sheet) - Not to exceed $880,000.00, from $21,319,817.00 to $22,199,817.00 - Financing: Water Construction Fund ($415,000.00) and Wastewater Construction Fund ($465,000.00) 

 

*In alignment with Water and Wastewater Capital Improvement Program.

 

Body

BACKGROUND

 

On October 12, 2022, the City Council authorized a construction services contract with Camino Construction, L.P. for the installation of water and wastewater mains at 32 locations. This action will authorize an increase in the construction services contract with Camino Construction, L.P. to complete miscellaneous work associated with water and wastewater main improvements at 17 locations throughout the city. The additional work is necessary to complete pipeline installations previously contracted with another vendor but not completed.

 

The additional work included in this action was originally part of four separate construction contracts with the Dallas Water Utilities Department (DWU) for the installation and replacement of water and wastewater mains at various locations. The original contractor had several payment disputes with their subcontractors, submitted unreasonable payment claims, and unilaterally demobilized without completing all the contracted work. Despite exhaustive efforts by DWU and the City Attorney to work with the contractor and surety company, neither has upheld their contractual obligation to complete the work, ultimately prompting the City to terminate the original contracts and pursue completion using other contractors.

 

The original contract with Camino Construction, L.P. provides the most efficient and cost-effective means to complete the remaining work abandoned by the previous contractor. Using the remaining balance of the contract and authorizing an additional amount of $880,000.00 will allow for completion of the remaining work. The locations associated with this action are in various stages of completion, needing miscellaneous work including sections of water and wastewater utility installation, water tie-in connections, final paving, and surface restoration.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          February 2026

Complete Construction                     July 2027

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On October 12, 2022, the City Council authorized a construction services contract with Camino Construction, L.P. for the installation of water and wastewater mains at 32 locations, by Resolution No. 22-1554.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

Water Construction Fund

$415,000.00

$0.00

$0.00

Wastewater Construction Fund

$465,000.00

$0.00

$0.00

Total

$880,000.00

$0.00

$0.00

 

Construction Contract                                           $21,319,817.00

Change Order No. 1(this action)                      $     880,000.00

 

                       Total Project Cost                                            $22,199,817.00

 

Council District                                                   Amount

 

2                            $    29,959.43

3                            $  352,255.06

6                            $  155,268.73

7                            $      6,454.81

8                            $      9,128.00

14                          $  326,933.97

 

Total                                  $ 880,000.00

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Camino Construction, L.P.

Non-local

78.43%

 

OWNER/EXECUTIVE

 

Camino Construction, L.P.

 

Rogelio Ayala, President

 

MAPS

 

Attached