File #: 19-1007    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/9/2019 In control: Water Utilities Department
On agenda: 9/11/2019 Final action:
Title: Authorize a professional services contract with Espey Consultants, Inc. dba RPS to provide engineering services for the design, construction administration, and start-up associated with the Large Valve and Meter Project (list attached to the Agenda Information Sheet) - Not to exceed $1,449,744.00 - Financing: Water Construction Fund ($1,303,699.10) and Wastewater Capital Improvement D Fund ($146,044.90)
Sponsors: District 1, District 3, District 4, District 6, District 8, District 9, District 10, District 11, Outside
Indexes: 1, 10, 11, 200, 3, 4, 6, 8, 9
Attachments: 1. List, 2. Map, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     September 11, 2019

COUNCIL DISTRICT(S):                     1, 3, 4, 6, 8, 9, 10, 11, Outside City Limits

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a professional services contract with Espey Consultants, Inc. dba RPS to provide engineering services for the design, construction administration, and start-up associated with the Large Valve and Meter Project (list attached to the Agenda Information Sheet) - Not to exceed $1,449,744.00 - Financing: Water Construction Fund ($1,303,699.10) and Wastewater Capital Improvement D Fund ($146,044.90)

 

Body

BACKGROUND

 

Dallas Water Utilities (DWU) owns and operates 55 water and wastewater meters vaults and associated appurtenances critical to the distribution, collection and metering of water and wastewater service for our wholesale customers. A condition assessment of these meter vaults was performed to identify and prioritize improvements to extend their service life, reduce operational and maintenance costs and improve worker safety.

 

Based on the results of the condition assessments, this action will authorize engineering services for the design, construction administration, and start-up of improvements to 14 customer City water and wastewater meter vaults. These underground vaults range in size from 100 to 400 square feet with a depth ranging from 10-25 feet. They also contain valves, meters, and monitoring equipment necessary to deliver water and collect wastewater from our wholesale customers.

 

This action also includes improvements to seven existing water distribution system control valves and the installation of two new water control valves. These valves are used by DWU to redirect water flows throughout the City based on demand and/or service outages. The installation of the two new valves will provide greater redundancy and flexibility for the overall system.

 

The consulting firm for this project was selected following a qualifications-based selection process in accordance with City of Dallas Administrative Directive 4-5 procurement guidelines.

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Design                     October 2019

Complete Design                     December 2020

Begin Construction                     January 2021

Complete Construction                     November 2022

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Water Construction Fund - $1,303,699.10

Wastewater Capital Improvement D Fund - $146,044.90

 

Estimated Future Cost - Construction - $16,000,000.00

 

                     Council District                     Amount

 

                       1                     $   188,364.00

                       3                     $   129,749.00

                       4                     $     68,698.00

                       6                     $     69,595.00

                       8                     $   214,085.00

                       9                     $     66,431.00

                     10                     $     83,972.00

                     11                     $   163,585.00

                     Outside City Limits                     $   465,265.00

 

                     Total                     $1,449,744.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$1,449,744.00

Architectural & Engineering

25.66%

19.88%

$288,163.00

This contract does not meet the M/WBE goal, but complies with good faith efforts.

 

 

 

 

 

OWNER

 

Espey Consultants, Inc. dba RPS

 

Peter Fearn, President and Chief Executive Officer

 

MAP

 

Attached