File #: 24-1856    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/29/2024 In control: Park & Recreation Department
On agenda: 6/26/2024 Final action:
Title: Authorize an increase in the construction services contract with RoeschCo Construction, LLC for the construction of the University Crossing Trail Lighting Project from Ellsworth Avenue to the Matilda Bridge - Not to exceed $201,278.75, from $1,235,000.00 to $1,436,278.75 - Financing: University Crossing PID Trail Fund
Indexes: 14
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life, Arts & Culture

AGENDA DATE:                     June 26, 2024

COUNCIL DISTRICT(S):                     14

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     John D. Jenkins

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with RoeschCo Construction, LLC for the construction of the University Crossing Trail Lighting Project from Ellsworth Avenue to the Matilda Bridge - Not to exceed $201,278.75, from $1,235,000.00 to $1,436,278.75 - Financing: University Crossing PID Trail Fund

 

Body

BACKGROUND

 

This action will authorize Change Order No. 1 to the construction services contract with RoeschCo Construction, LLC for the construction of the University Crossing Trail Lighting Project from Ellsworth Avenue to the Matilda Bridge to improve lighting at Glencoe Park. The original scope of work includes installing light poles from Glencoe Park to Matilda Bridge.

 

This change order scope includes the installation of nine additional light poles, including the construction of drilled pier footings, light pole bases, fixtures, and wiring along the trail alignment starting from Martel Avenue to Ellsworth Avenue along the University Crossing Trail.

 

This change results in an increase for additional work scope in the amount of $201,278.75 increasing the contract amount from $1,235,000.00 to $1,436,278.75.  Change Order No. 1 adds 180 days to the contract time.

 

The University Crossing Public Improvement District (UCPID) has an agreement in place with the Texas Department of Transportation to fully fund the required matching funds, not to exceed $795,395.00.

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                     November 2023

Complete Construction                     August 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On January 14, 2021, the Park and Recreation Board authorized an Advance Funding Agreement (AFA) with the TxDOT for a TA Set-Aside Program Project (Agreement No. CSJ 0918-47-204, CFDA No. 20.205) to accept funding for construction of the University Crossing Trail Lighting Project, in the amount of $1,024,444.00.

 

On January 14, 2021, the Park and Recreation Board authorized an agreement with UCPID to accept funding for construction of the University Crossing Trail Lighting Project, in an amount not to exceed $795,935.00.

 

On February 10, 2021, the City Council authorized: (1) an AFA with TxDOT for a TA Set-Aside Program Project (Agreement No. CSJ 0918-47-204, CFDA No. 20.205) for construction of the University Crossing Trail Lighting Project in the amount of approximately $1,024,444.00, of which the Federal portion is $687,280.00, State participation is $41,769.00, and the City of Dallas’ local match is $295,395.00; (2) a portion of the required local match in the amount of $27,335.00 to be paid by warrant check to the State at the beginning of the project; (3) the establishment of appropriations in the amount of $687,280.00 in the University Crossing PID Trail Fund (in addition to direct State participation in the amount of $41,769.00); (4) the receipt and deposit of TA Set-Aside Program Funds in the amount of $687,280.00 in the University Crossing PID Trail Fund; (5) allocation of $295,395.00 in the University Crossing PID Trail Fund as the City of Dallas’ local match; and (6) execution of the agreement including all terms, conditions, and documents required by the agreement by Resolution No. 21-0329.

 

On April 20, 2023, the Park and Recreation Board authorized a construction services contract for the University Crossing Trail Lighting Project from Ellsworth Avenue to the Matilda Bridge with RoeschCo Construction, LLC.

 

On May 24, 2023, the City Council authorized a construction services contract with RoeschCo Construction, LLC for University Crossing Trail Lighting Project from Ellsworth Avenue to Matilda Bridge, in an amount not to exceed $1,235,000.00 by Resolution No. 23-0718.

 

On June 20, 2024, the Park and Recreation Board will consider authorizing an increase in the construction services contract with RoeschCo Construction, LLC.

 

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

University Crossing PID Trail Fund

$201,278.75

$0.00

$0.00

 

 

Construction Contract                                          $1,235,000.00

Change Order No. 1 (this action)                                          $   201,278.75

 

Total amount not to exceed                                          $1,436,278.75

 

 

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$201,278.75

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

0.00%

100.00%

$201,278.75

This item does not meet the M/WBE subcontracting goal, however, the prime is a WBE.

Select the BID Policy Outcome

RoeschCo Construction, LLC - Non-local; Workforce - 0.00% Local

 

OWNER

 

RoeschCo Construction, LLC

9801 Camfield Avenue, Suite 200

Frisco, Texas 75033

 

Marcie Roeschley, President

 

MAP

 

Attached