Title: Authorize a professional services contract with Simon Engineering & Consulting, Inc. to provide engineering services for the design of six local streets as part of Street Reconstruction Group 24-2001 (list attached to the Agenda Information Sheet) - Not to exceed $525,563.18 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($491,260.78), Water Capital Improvement G Fund ($18,830.02), and Wastewater Capital Improvement G Fund ($15,472.38) *In alignment with Infrastructure Management Plan.
Indexes: 1, 2, 4, 8
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     June 24, 2026

COUNCIL DISTRICT(S):                     1, 2, 4, 8

DEPARTMENT:                     Department of Transportation and Public Works

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize a professional services contract with Simon Engineering & Consulting, Inc. to provide engineering services for the design of six local streets as part of Street Reconstruction Group 24-2001 (list attached to the Agenda Information Sheet) - Not to exceed $525,563.18 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($491,260.78), Water Capital Improvement G Fund ($18,830.02), and Wastewater Capital Improvement G Fund ($15,472.38)

 

*In alignment with Infrastructure Management Plan.

 

Body

BACKGROUND

 

The Request for Qualifications CIZ24-PBW-3124 was issued on October 9, 2024, for the 2024 Bond Program Capital Improvements Projects. The consulting firm, Simon Engineering & Consulting, Inc. was selected following the qualifications-based selection process in accordance with the City of Dallas procurement guidelines.

 

This action will authorize a professional services contract with Simon Engineering & Consulting, Inc.  to provide engineering services for the design of six local streets as part of Street Reconstruction Group 24-2001. The street reconstruction projects will include replacing the existing deteriorating concrete streets with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, possible replacement of drainage system, and water and wastewater improvements.

 

 

 

 

 

 

 

 

 

The following are the locations for each project:

 

Street Reconstruction - Local Streets - Improvements

 

Project                                                                                                                              Council District                 

 

200 Beckley Hills Drive from 100                                                                                    8                                                               

Beckley Hills Drive to End of Pavement                                          

 

2900-3000 Hudnall Street from                                                                                     2                                                               

Bradford Drive to Cedar Springs Road                     

 

1000 Forester Drive from Fernwood Avenue                                          4                                                               

to Whitaker Avenue                      

 

2800 Virgil Street from South Crowdus Street                                          2                                                               

to South Malcolm X Boulevard

 

1000 Centre Street from South Polk Street                                          1                                          

 to A01767

 

1800-2000 Emmett Street from South Waverly Drive                     1                                                               

 to South Oak Cliff Boulevard

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Design                                                               August 2026

Complete Design                                           August 2027

Begin Construction                                           January 2028

Complete Construction                       January 2030

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

Street and Transportation (A) Fund (2024 General Obligation Bond Fund)

$491,260.78

$0.00

$0.00

Water Capital Improvement G Fund

$  18,830.02

$0.00

$0.00

Wastewater Capital Improvement G Fund

$  15,472.38

$0.00

$0.00

Total

$525,563.18

$0.00

$0.00

 

 

 

 

 

 

Council District                                           Amount

 

                      1                                                               $190,529.81

2                                                               $163,571.26

4                                                               $  67,028.18

8                                                               $104,433.93

 

Total                                                               $525,563.18

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Simon Engineering & Consulting, Inc.

Local

100.00%

 

 

OWNER/EXECUTIVE

 

Simon Engineering & Consulting, Inc.

 

Voranique “Nikki” Simon, P.E., President

 

MAPS

 