Skip to main content
Dallas Logo
File #: 24-1277    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/5/2024 In control: Water Utilities Department
On agenda: 5/8/2024 Final action:
Title: Authorize an increase in the construction services contract with Douglas Dailey Construction, LLC for the emergency replacement of an 18-inch diameter sanitary sewer pipeline at 10750 Maylee Boulevard - Not to exceed $412,280.00, from $14,672,145.00 to $15,084,425.00 - Financing: Wastewater Capital Improvement F Fund
Indexes: 9
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     May 8, 2024

COUNCIL DISTRICT(S):                     9

DEPARTMENT:                     Water Utilities Department

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Douglas Dailey Construction, LLC for the emergency replacement of an 18-inch diameter sanitary sewer pipeline at 10750 Maylee Boulevard - Not to exceed $412,280.00, from $14,672,145.00 to $15,084,425.00 - Financing: Wastewater Capital Improvement F Fund

 

Body

BACKGROUND

 

The existing concrete sewer at 10750 Maylee Boulevard was built in 1955 and has structurally failed. Dallas Water Utilities (DWU) Wastewater Collection investigated a Sanitary Sewer Overflow (SSO) that occurred on March 23, 2024. The investigation revealed the cause of the SSO was a structural failure of the 18-inch diameter sanitary sewer mainline located at 10750 Maylee Boulevard near the intersection of Ferguson Road.

 

DWU approached Douglas Dailey Construction, LLC, who has extensive experience and expertise with pipe bursting technology for a cost proposal to complete the work. Douglas Dailey Construction, LLC submitted a final cost proposal of $412,280.00. The estimate was reviewed by DWU and found to be a reasonable cost for the significance and difficulty of the work to be performed. Given the failure of the existing pipeline and threat of another SSO occurrence, DWU needs to immediately move forward with the pipe replacement.

 

This action will ratify additional construction services for the immediate emergency replacement of approximately 460 feet of 18-inch diameter sanitary sewer mainline. The location is within a commercial zone including several businesses such as RaceTrac, Texaco, and a strip mall and as a result has a very high traffic volume. The replacement will be completed using a trenchless pipe bursting method to minimize significant impacts to the surrounding businesses and traffic.

 

 

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Construction                             June 2022

Complete Construction    June 2024

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On May 25, 2022, the City Council authorized a construction services contract for the replacement and rehabilitation of approximately 27,944 feet of water and wastewater mains at 13 locations by Resolution No. 22-0816.

On April 10, 2024, the City Council authorized an increase in the construction services contract for additional work associated with the installation of water services, large valve manholes, dewatering efforts for construction, and additional paving and surface restoration work by Resolution No. 24-627.

FISCAL INFORMATION

 

Fund

FY 2024

FY 2025

Future Years

Wastewater Capital Improvement F Fund

$412,280.00

$0.00

$0.00

 

Construction                     $13,921,735.00

Change Order No. 1                     $     750,410.00

Change Order No. 2 (this action)                     $     412,280.00

                     

Total                     $15,084,425.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Procurement Category

M/WBE Goal

$412,280.00

Construction

32.00%

M/WBE Subcontracting %

M/WBE Overall %

M/WBE Overall Participation $

34.00%

34.00%

$140,175.20

This contract exceeds the M/WBE goal.

Change Order No. 2 - 34.00% Overall MWBE participation

Douglas Dailey Construction, LLC - Non-Local, Workforce - 22.86% Local

 

 

 

 

 

 

OWNER

 

Douglas Dailey Construction, LLC

 

Douglas Dailey, President

 

MAP

 

Attached