File #: 26-20A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 11/17/2025 In control: Dallas Water Utilities Department
On agenda: 1/14/2026 Final action:
Title: Authorize an increase in the construction services contract with Camino Construction, LP, for storm drainage system improvements in Reverchon Drive from Mateur Street to Avon Street - Not to exceed $1,254,100.00, from $11,631,673.00 to $12,885,773.00 - Financing: Storm Drainage Management Capital Construction Fund *In alignment with Capital Improvement Program.
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     January 14, 2026

COUNCIL DISTRICT(S):                     1

DEPARTMENT:                     Dallas Water Utilities Department

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize an increase in the construction services contract with Camino Construction, LP, for storm drainage system improvements in Reverchon Drive from Mateur Street to Avon Street - Not to exceed $1,254,100.00, from $11,631,673.00 to $12,885,773.00 - Financing: Storm Drainage Management Capital Construction Fund

 

*In alignment with Capital Improvement Program.

 

Body

BACKGROUND

 

On September 11, 2024, the City Council authorized a construction services contract with Camino Construction, LP for the installation of water and wastewater main improvements at 21 locations. Prior to the beginning of construction at one of the locations, Reverchon Drive from Overcrest Street to Avon Street, it was determined that storm drainage improvements were needed to alleviate flooding in the area in addition to the proposed water and wastewater main improvements. To avoid excavation of recently restored pavement and to limit disruption to the public for multiple improvement projects, it was decided to delay the water and wastewater improvements and expedite the design of storm drainage improvements. The storm drainage improvements have been designed and will be installed under the same construction contract as the water and wastewater improvements.

 

This action will authorize an increase in the construction services contract with Camino Construction, LP, to include the proposed storm drainage system improvements in Reverchon Drive from Mateur Street to Avon Street. Camino Construction, LP, has provided an acceptable proposal to complete the additional work. The additional cost is less than the engineer’s opinion of probable cost and represents a good value for the storm drainage improvement work. The improvements include 24, 30, and 36-inch diameter storm drains, inlets, and a box culvert in Reverchon Drive, inlets and connecting storm drains in El Tivoli Drive and Overcrest Street, and a box culvert and outfall structure to Coombs Creek. Following completion of the utility work, Dallas Water Utilities will coordinate with Transportation and Public Works for paving restoration and paving improvements in the area.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                     February 2026

Complete Construction                     July 2026

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On September 11, 2024, the City Council authorized a construction services contract with Camino Construction, LP for the installation of water and wastewater mains at twenty-one locations by Resolution No. 24-1305.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

Storm Drainage Management Capital Construction Fund

$1,254,100.00

$0.00

$0.00

 

Construction                                                                                    $11,631,673.00

Change Order No. 1 (this action)                     $  1,254,100.00

 

Total                                                               $12,885,773.00

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Camino Constructions, LP

Non-local

78.43%

 

OWNER/EXECUTIVE

 

Camino Constructions, LP

 

Rogelio Ayala, President

 

MAP

 

Attached