File #: 25-2519A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 8/5/2025 In control: Department of Transportation and Public Works
On agenda: 9/10/2025 Final action:
Title: Authorize Contract Amendment No. 1 to the construction services contract with XIT Paving & Construction, Inc. for the construction of the Five Mile Infrastructure Improvements Package A Project to increase the contract amount in the amount of $842,353.00 (list attached to the Agenda Information Sheet) - Not to exceed $842,353.00, from $11,564,976.75 to $12,407,329.75 - Financing: Wastewater Construction Fund ($115,880.00), Water Construction Fund ($232,793.00), and 2024B Certificates of Obligation Fund ($493,680.00)
Indexes: 8
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     September 10, 2025

COUNCIL DISTRICT(S):                     8

DEPARTMENT:                     Department of Transportation and Public Works

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize Contract Amendment No. 1 to the construction services contract with XIT Paving & Construction, Inc. for the construction of the Five Mile Infrastructure Improvements Package A Project to increase the contract amount in the amount of $842,353.00 (list attached to the Agenda Information Sheet) - Not to exceed $842,353.00, from $11,564,976.75 to $12,407,329.75 - Financing: Wastewater Construction Fund ($115,880.00), Water Construction Fund ($232,793.00), and 2024B Certificates of Obligation Fund ($493,680.00)

 

Body

BACKGROUND

 

On February 28, 2024, the City Council authorized the construction services contract with XIT Paving & Construction, Inc. for Five Mile Infrastructure Improvements Package A Project by Resolution No. 24-0327.

 

The scope of work includes replacing the existing deteriorating streets with reinforced concrete pavement, curb and gutter, sidewalk, driveway approaches, drainage improvements, water and wastewater improvements, illumination, and other miscellaneous items necessary to complete the project, in accordance with plans and specifications.

 

Due to the delays in securing the United States Housing and Urban Development (HUD) Environmental Clearance and Right-Of-Way  and Easement acquisition, the project could not begin as scheduled. Consequently, the contractor, XIT Paving & Construction, Inc. requested additional funding in the amount of $842,353.00 to cover the price inflation in construction materials, equipment, and labor.

 

This action will authorize Contract Amendment No. 1 to the construction services contract with XIT Paving & Construction, Inc.  for the additional funding needed to complete the Five Mile Infrastructure Improvements Package A Project.

 

The following are the locations and additional construction costs for each project:

 

Project                                                                                                          Council District                                                Amount

 

Tracy Road from Givendale Road

 to Persimmon Road                                                                                     8                                                                $ 305,940.00

 

Givendale Road from Lancaster Road

to Tracy Road                                                                                                          8                                                                      $  133,792.00

 

Pall Mall Avenue from Lancaster Road

to Tracy Road                                                                                                          8                                                                      $ 402,621.00

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                             October 2025

Complete Construction    October 2027

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On June 9, 2021, the City Council authorized the adoption of the FY 2021-22 Consolidated Plan Budget, by Resolution No. 21-0974.

 

On June 22, 2022, the City Council authorized the adoption of the FY 2022-23 Consolidated Plan Budget, by Resolution No. 22-1024.

 

On June 14, 2023, the City Council authorized the adoption of the FY 2023-24 Consolidated Plan Budget, by Resolution No. 23-0765.

 

On February 28, 2024, the City Council authorized the construction services contract XIT Paving & Construction, Inc. for Five Mile Infrastructure Improvements Package A project in the amount of $11,564,976.75 by Resolution No. 24-0327.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Wastewater Construction Fund

$115,880.00

$0.00

$0.00

Water Construction Fund

$232,793.00

$0.00

$0.00

2024B Certificates of Obligation

$493,680.00

$0.00

$0.00

Total

$842,353.00

$0.00

$0.00

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

XIT Paving & Construction, Inc.

Non-local

0.00%

 

 

OWNER/EXECUTIVE

 

XIT Paving & Construction, Inc.

 

Doug Spradley, Vice President

 

MAPS

 

Attached