Title: Authorize a professional services contract with LJA Engineering, Inc. to provide engineering services for flood management and storm drainage system improvements at six locations (list attached to the Agenda Information Sheet) - Not to exceed $829,323.02 - Financing: 2025 Certificate of Obligation Fund
Indexes: 1, 13, 4
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Sustainable

AGENDA DATE:                     September 24, 2025

COUNCIL DISTRICT(S):                     1, 4, 13

DEPARTMENT:                     Dallas Water Utilities Department

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize a professional services contract with LJA Engineering, Inc. to provide engineering services for flood management and storm drainage system improvements at six locations (list attached to the Agenda Information Sheet) - Not to exceed $829,323.02 - Financing: 2025 Certificate of Obligation Fund

 

Body

BACKGROUND

 

At Brooklyndell Avenue, a new bridge class culvert will be designed to replace the existing bridge at Coombs Creek. For Polk Street, the scope of services includes the design of a new culvert including custom headwalls, the extension of curb and gutter, improved street drainage and channel improvements upstream and downstream of the culvert. The contract also includes comprehensive drainage studies and conceptual designs to select feasible solutions to convey the 100-year storm event at the Coombs Creek Bridge at North Plymouth Road, Cedar Creek Bridge at South Tyler Street, Cedar Creek Channel between the ATSF Railroad and Ewing Avenue, and the Holland Avenue at Miles Street area. Several flood management and storm drainage options will be modeled for each area and recommended alternatives will be selected for further development of comprehensive design improvements. A future supplemental agreement or separate contract will be necessary to complete the design of recommended improvements at these locations.

 

The services provided for this contract include project management, topographic and boundary surveys, subsurface utility exploration, hydrologic and hydraulic studies, alternative analysis, development of conceptual and preliminary construction plans, structural analysis, and development of pre-final and final construction plans and special specifications. The consulting firm for this project was selected following a qualifications-based selection process in accordance with City of Dallas Administrative Directive 4-05 procurement guidelines.

 

This action will authorize a professional services contract with LJA Engineering, Inc. for the engineering evaluation and design of flood management and storm drainage system improvements including bridge, culvert, channel and storm sewer improvements at six locations. These areas were identified to have inadequate infrastructure to limit flooding impacts. The locations include Brooklyndell Avenue and North Plymouth Road along Coombs Creek, South Tyler Street and Polk Street at Cedar Creek, Cedar Creek Channel between Ewing Avenue and the Atchison, Topeka and Santa Fe (ATSF) Railroad, and the Holland Avenue at Miles Street area.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Services                                                               October 2025

Complete Services                                                               March 2028

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

2025 Certificate of Obligation Fund

$829,323.02

$0.00

$0.00

 

Council District                                                                Amount

 

                     1                                                                                    $611,781.39

           4                                                                                    $  88,188.90

          13                                                                                    $129,352.73

 

        Total                                                                                    $829,323.02

 

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

LJA Engineering, Inc.

Local

6.01%

 

OWNER/EXECUTIVE

 

LJA Engineering, Inc.

 

James D. Ross, President

 

 

MAPS

 