File #: 23-2170    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/21/2023 In control: Department of Public Works
On agenda: 12/13/2023 Final action:
Title: Authorize an Advance Funding Agreement with the Texas Department of Transportation (CSJ No. 0918-47-275), in the amount of $8,657,259.00, for the preliminary engineering plans, specifications and estimates, and construction of sidewalks and bicycle lanes on West Commerce Street from Fort Worth Avenue to Riverfront Boulevard - Financing: No cost consideration to the City (see Fiscal Information)
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     December 13, 2023

COUNCIL DISTRICT(S):                     6

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Dr. Robert Perez

______________________________________________________________________

SUBJECT

 

title

Authorize an Advance Funding Agreement with the Texas Department of Transportation (CSJ No. 0918-47-275), in the amount of $8,657,259.00, for the preliminary engineering plans, specifications and estimates, and construction of sidewalks and bicycle lanes on West Commerce Street from Fort Worth Avenue to Riverfront Boulevard - Financing: No cost consideration to the City (see Fiscal Information)

 

body

BACKGROUND

 

The West Commerce Street from Fort Worth Avenue to Riverfront Boulevard Project is a partnership project between the City of Dallas and the Texas Department of Transportation (TxDOT) to construct sidewalks and bicycle lanes. The City is the lead agency to administer the design and construction of the project. This project is needed to provide greater opportunity for multi-modal travel and improve safety in the area.

 

On August 30, 2018, The Texas Commission passed Minute Order Nos. 115291 and 115292 authorizing the State to undertake and complete a highway improvement or other transportation projects generally described as bicycle and pedestrian improvements.

 

This action will authorize a Local Project Advanced Funding Agreement (LPAFA) with TxDOT for the engineering review and construction administration costs associated with this project. The estimated total project cost is $8,657,259.00 to be 100 percent funded by federal and state funds.

 

If this LPAFA is not approved at this time, the project will be delayed, which may jeopardize the federal funding that has been allocated to the project. Without federal funding, it will be unfeasible for the City to proceed with the project.

 

 

 

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Design                     December 2024

Complete Design                     July 2026

Begin Construction                     January 2027

Complete Construction                     January 2029

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

No cost consideration to the City.  The local government participation amount requirement for federally eligible items of work is waived in full.  The City of Dallas will commit to spending City Funds for any non-eligible items of work.

 

Estimated Project Cost

 

Design                     $   528,650.00

Construction                     $7,658,650.00

Direct State Cost                     $     82,700.00

Indirect State Cost                     $   387,259.00

 

Total Estimated Cost                     $8,657,259.00

 

Funding Sources

 

State Participation                     $   387,259.00

Federal TxDOT Participation                     $8,270,000.00

 

Total                     $8,657,259.00

 

MAP

 

Attached