File #: 25-20A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 11/22/2024 In control: Department of Transportation and Public Works
On agenda: 1/8/2025 Final action:
Title: Authorize (1) an agreement with Archway Bonnie View 49, Ltd. for contribution of funds towards the warranted traffic signal installation at the intersection of Bonnie View Road and Langdon Road in the city of Dallas; (2) an increase in appropriations in an amount not to exceed $25,000.00 in the Transportation Special Projects Fund; and (3) the receipt and deposit of funds in an amount not to exceed $25,000.00 in the Transportation Special Projects Fund - Not to exceed $25,000.00 - Financing: Transportation Special Projects Fund
Indexes: 8
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Transportation & Infrastructure

AGENDA DATE:                     January 8, 2025

COUNCIL DISTRICT(S):                     8

DEPARTMENT:                     Department of Transportation and Public Works

EXECUTIVE:                     Dev Rastogi

______________________________________________________________________

SUBJECT

 

Title

Authorize (1) an agreement with Archway Bonnie View 49, Ltd. for contribution of funds towards the warranted traffic signal installation at the intersection of Bonnie View Road and Langdon Road in the city of Dallas; (2) an increase in appropriations in an amount not to exceed $25,000.00 in the Transportation Special Projects Fund; and (3) the receipt and deposit of funds in an amount not to exceed $25,000.00 in the Transportation Special Projects Fund - Not to exceed $25,000.00 - Financing: Transportation Special Projects Fund

 

Body

BACKGROUND

 

Archway Bonnie View 49, Ltd. (Developer) desires the development or redevelopment of property located at 8201 Bonnie View Road, Dallas, Texas 75241 for commercial distribution/warehouse facilities (“Development Project”). The Development Project contributes to the need for municipal infrastructure additions or improvements, namely a warranted traffic signal at the intersection of Bonnie View Road and Langdon Road.

 

The City of Dallas, pursuant to Chapter 51A-1.109 of the Dallas City Code, determines the city infrastructure has an estimated total cost of Six Hundred Fifty Thousand and No/100 ($650,000.00) and made an apportionment determination in accordance thereof as to the Developer and City’s cost participation. The impact created by the Development Project requires the installation of city infrastructure requiring the Developer to provide proportionate share of the costs for the installation of city infrastructure. The Developer agrees to provide its proportionate share towards the city infrastructure to address the municipal infrastructure needs created by their planned Development Project as determined by Section 51A-1.109 of the Dallas City Code, in the amount of $25,000.00.

 

This item will authorize the receipt and disbursement of funds towards the warranted traffic signal installation.

 

 

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2025

FY 2026

Future Years

Transportation Special Projects Fund

$25,000.00

$0.00

$0.00

 

Note: The total estimated project cost is $650,000.00. A majority of funding will come from various developer contributions, and any remaining cost will be paid for by the City.

 

MAP

 

Attached