Legislation Details

File #: 26-2511A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 7/29/2026 In control: Dallas Water Utilities Department
On agenda: 9/23/2026 Final action:
Title: Authorize a construction services contract for the installation and rehabilitation of water and wastewater mains at eighteen locations (list attached to the Agenda Information Sheet) – Douglas Dailey Construction, LLC, lowest responsible bidder of ten - Not to exceed $10,653,390.90 - Financing: Wastewater Capital Improvement F Fund ($6,494,392.90), Water (Drinking Water) – 2024C Water Revenue Bonds TWDB LM241535 Fund ($3,082,115.00), and Water Capital Improvement G Fund ($1,076,883.00) *In alignment with Water and Wastewater Capital Improvement Program.
Indexes: 1, 14, 2, 4, 6, 7, 8, 9
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

PILLAR:                     Sustainable

AGENDA DATE:                     September 23, 2026

COUNCIL DISTRICT(S):                     1, 2, 4, 6, 7, 8, 9, 14

DEPARTMENT:                     Dallas Water Utilities Department

PRIORITY:                     Infrastructure

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction services contract for the installation and rehabilitation of water and wastewater mains at eighteen locations (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of ten - Not to exceed $10,653,390.90 - Financing: Wastewater Capital Improvement F Fund ($6,494,392.90), Water (Drinking Water) - 2024C Water Revenue Bonds TWDB LM241535 Fund ($3,082,115.00), and Water Capital Improvement G Fund ($1,076,883.00)

 

*In alignment with Water and Wastewater Capital Improvement Program.

 

Body

BACKGROUND

 

This action will authorize a construction services contract for the installation and rehabilitation of approximately 27,787 feet of water and wastewater mains ranging in size from 8-inch to 18-inch in diameter. The scope of the work includes the installation of approximately 8,979 feet of 8-inch and 1,114 ft of 12-inch diameter water mains as well as the installation and rehabilitation of approximately 14,321 feet of 8-inch, 2,838 feet of 12-inch, and 535 feet of 18-inch diameter wastewater mains.

 

The existing water and wastewater mains were built between 1901 and 1959. These mains are contributing to an increase in maintenance costs, as well as service interruptions. The installation of the proposed segments will improve the capacity of the water and wastewater systems and reduce maintenance costs.

 

The chart below outlines Douglas Dailey Construction, LLC's contractual activities with the City of Dallas over the past three years:

 

                                                                                                                                                   PBW                     DWU                     PKR                     TRN

 

Projects Completed                                                                                                            0                        2                       0                       0

Active Projects                                                                                                            0                        5                       0                       0

Change Orders                                                                                                            0                        2                       0                       0

Projects Requiring Liquidated Damages                                             0                        0                       0                       0

Projects Completed by Bonding Company                        0                        0                       0                       0

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                          January 2027

Complete Construction                     January 2029

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

Information about this item was provided to the Transportation and Infrastructure Committee on September 14, 2026.

 

FISCAL INFORMATION

 

Fund

FY 2026

FY 2027

Future Years

Wastewater Capital Improvement F Fund

$6,494,392.90

$0.00

$0.00

Water (Drinking Water) - 2024C Water Revenue Bonds TWDB LM241535 Fund

$3,082,115.00

$0.00

$0.00

Water Capital Improvement G Fund

$1,076,883.00

$0.00

$0.00

Total

$10,653,390.90

$0.00

$0.00

 

Council District                                                Amount

 

1                      $     322,891.95

                     2                               $   1,865,319.23

4                      $     804,297.14

6                                                                $     455,916.96

7                                                                $  4,236,864.18

8                                                                $  1,146,551.42

9                                                                $     634,626.43

14                                                                $  1,186,923.59

 

Total                                                                $10,653,390.90

 

LOCAL PARTICIPATION

 

Prime

Status

Workforce %

Douglas Dailey Construction, LLC

Local

28.57%

 

 

 

 

 

 

 

 

 

 

PROCUREMENT INFORMATION

 

The following ten bids with quotes were received on July 17, 2026:

 

*Denotes successful bidder

 

Bidders                                                                                                                                                                         Bid Amount

 

*Douglas Dailey Construction, LLC                                                                                    $10,653,390.90

 2005 Bluff Springs Road,

 Ferris, Texas 75125

Camino Construction, L.P.                                                                                                                                    $11,653,171.00

Estrada Concrete Company, LLC                                                                                                             $11,704,069.00

C-Con Services, Inc.                                                                                                                              $11,789,770.00

Western Municipal Construction of Texas, LLC                                                               $12,745,114.50
SYB Construction Co., Inc.
                                                                                                                              $13,200,453.31

Muniz Construction, Inc.                                                                                                                              $13,858,997.00

Omega Contracting, LLC                                                                                                                              $14,374,922.00

Mach Energy Services, LLC                                                                                                         $16,179,861.00

John Burns Construction Company of Texas                                                               $17,995,393.00

 

OWNER/EXECUTIVE

 

Douglas Dailey Construction, LLC

 

Jose Sura, President

 

MAPS

 

Attached